Hardware-design
Deutschmann Automation GmbH & Co. KG
14
UNIGATE
®
CX V. 1.4
2.10.19
4.4 UNIGATE
®
CX design
4.5 Operation modes
4.5.1
RUN-operation (data exchange mode)
In the ex-works condition the device is set to RUN-operation.
In RUN-operation it is possible to use the Debug-interfaces of the UNIGATE
®
CLs.
With these interfaces it is possible to execute a Script step-by-step and in a normal case they are
only necessary for developing a Script. Furthermore the device can be configured through these
interfaces. To do so, the software WINGATE is used ("Extras" -> "Upload_Config_Debug" or
"Download_Config_Debug")
The Debug-interfaces are connected with X1 pin 3 + 4 or X2 pin 3 + 4.
Further information on how to use the Debug-interface can be found in the instruction manual
UNIGATE
®
CL for the respective Fieldbus.
4.5.2
Test mode
Setting of the test mode
The test mode is set by bringing the switches S4 and S5 in position "E". All other switches will not
be taken into consideration for the setting of the test mode. Now the Gateway has to be restarted
with these settings (by a short disconnection from the power supply).
In the test mode the Gateway always operates with the settings 9600 baud, no parity, 8 databits
and 1 stopbit.
The test mode may be helpful to integrate the Gateway in the relevant environment.