FLASHING INSTALLATION: 
 (V6F-8DM or V6F-8DM) 
 

Determine the flashing to be used with the roof-opening chart.  
Slide flashing over pipe until base is flat against roof.  Replace 
as many shingles as needed to cover exposed area and flashing 
base.  Secure in position by nailing through shingles (see 
figure 19). DO NOT NAIL THROUGH FLASHING CONE. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

STORM COLLAR INSTALLATION: (VSC1-8DM) 

 
Place storm collar over pipe and slide down until it is snug 
against the open edge of the flashing (see figure 20). 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Apply waterproof caulking to all seams and notches around 
storm collar and also at base around shingles. 
 

TERMINATIONS: 

STANDARD INSTALLATONS: 
 
The fireplace system must be terminated with the listed round 
top or square chase terminations.  The terminations approved 
for this fireplace are RTL-8DM, which can be used for 
flashing or chase and ETL-8DM for chase style termination 
only.  Figure 21 shows an RTL-8DM round top termination.  
 
 

FOLLOW THE INSTALLATION INSTRUCTIONS 
PROVIDED WITH THE TERMINATION BEING USED. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
CHASE INSTALLATIONS: 

 
Instructions for chase installations are included with the chase 
style termination chosen.  In a multiple chase installation, be 
sure to provide adequate distance between terminations to 
prevent smoke spillage from one termination to another.  It is 
recommended that terminations be separated at least 24 
inches, center-to-center, and stacked at vertical height 
difference of 18 inches or more (see figure 22). 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

10-FOOT RULE: 

 
All flue gas outlets of chimney terminations must extend a 
minimum of three feet in height above the highest point where 
it passes through the roof and must be at least two feet above 
the highest point of the roof that is within a horizontal distance 
of ten feet (see figure 23). 
 

 

Figure 19         FLASHING INSTALLATION 

Figure 20   STORM COLLAR INSTALLATION 

 

Figure 22    MULTIPLE CHASE TERMINATIONS 

 

Figure 21     TERMINATION INSTALLATION 

f i r e - p a r t s . c o m

Summary of Contents for VANGUARD V36NCL

Page 1: ...ted VI36NCL Left Side Opening Fully Insulated INSTALLATION INSTRUCTIONS This Fireplace is approved for use as a Wood Burning Fireplace or for use with a vented gas log approved to ANS Z21 60 Z21 84 or...

Page 2: ...HE FIREPLACE PG 3 8 HEARTH EXTENSION PG 3 9 OUTSIDE AIR KIT PG 4 10 GAS LINE INSTALLATION PG 4 11 VENT FREE GAS LOG INSTALLATION PG 5 12 COLD CLIMATE INSTALLATIONS PG 5 13 CHIMNEY PIPE PG 6 7 14 PENET...

Page 3: ...ON is the most important step in ensuring safe and continuous operation of this fireplace SELECTING LOCATION To determine the safest and most efficient location for your fireplace consider the followi...

Page 4: ...n hearth extensions not supplied and under the bottom front edge of the fireplace to protect against glowing embers falling through If the fireplace is to be installed on a raised platform a Z type em...

Page 5: ...ssed through an exterior wall Model AK4 or a vented crawl space Model AK4F See figure 5 and Accessories on page 11 Avoid installing outside air eyebrow in areas where inlet opening may be blocked by s...

Page 6: ...talled when using an unvented gas log set see accessories on page 11 VENTED GAS LOG INSTALLATION If you install a decorative gas appliance vented gas log the decorative gas appliance must comply with...

Page 7: ...ipe segments planned for maximum adaptability to individual site requirements Actual lengths gained lineal gain after fitting overlaps must be taken into consideration see figure 11 Each double wall c...

Page 8: ...c space as required by most codes When the double wall pipe passes through a framed opening into an attic space the firestop must be place into the attic floor as in figure 15 When the pipe passes thr...

Page 9: ...he correct opening length and flashing required STEP 4 Remove the shingles around the opening measured and cut out this section STEP 5 Add the next sections of the pipe until the end penetrates the ro...

Page 10: ...r chase and ETL 8DM for chase style termination only Figure 21 shows an RTL 8DM round top termination FOLLOW THE INSTALLATION INSTRUCTIONS PROVIDED WITH THE TERMINATION BEING USED CHASE INSTALLATIONS...

Page 11: ...t 9 inches above the opening of the fireplace see figure 24 Combustible materials above 9 inches and projecting more than 1 inches from the front face of the fireplace must be place at least 12 inches...

Page 12: ...www desatech com Desa International 2701 Industrial Drive P O Box 90024 Bowling Green KY 42102 9004 www desatech com 800 323 5190 ACCESSORY PARTS REPLACEMENT PARTS CONTACT YOUR LOCAL DEALER CONTACT YO...

Reviews: