Figure 13 Install server on sliding rail assemblies
7. Push the server into the cabinet. The slam latch on either side of the server
engage automatically as the server is pushed into the cabinet (1).
Note
The slam latches are released by pulling up on the latches (2). To secure the
server for unstable environments, locate the hard-mount screw under each
latch and tighten each screw with a #2 Phillips screwdriver (3).
Figure 14 Secure the server in the cabinet
1U1N Configuration Equipment Installation
36
Hardware Installation Guide
Summary of Contents for EMC VxFlex Ready Node 13G
Page 1: ...Dell EMC VxFlex Ready Node 13G Hardware Installation Guide 302 002 955 REV 05 ...
Page 6: ...FIGURES 6 Hardware Installation Guide ...
Page 8: ...TABLES 8 Hardware Installation Guide ...
Page 16: ...1U1N Procedures 16 Hardware Installation Guide ...
Page 58: ...2U1N Procedures 58 Hardware Installation Guide ...
Page 69: ...Figure 32 Install the bezel 2U1N Configuration Equipment Installation Install bezel 69 ...
Page 70: ...2U1N Configuration Equipment Installation 70 Hardware Installation Guide ...