5 Commissioning
Prior to initial switch-on of the filter check the wiring for completeness, short-circuit and earth fault.
If the wiring is not correct, a non-intended operation of controller and/or filter is possible.
First powering up
1.
Switch on mains supply :
- The filter is ready for operation at once.
2.
Check the readiness of the frequency converter:
- Proceed in accordance with the operating instructions of the frequency converter.
AHF 005/010 Operating Instructions
5 Commissioning
MG.80.C2.02 - VLT
®
is a registered Danfoss trademark
25
5