10 DKDHR
VI.GP.B1.02
Danfoss District Energy
Instructions
Kompakt H 28/35/42
7.0 Mounting
7.1 Protective cardboard and film wrapping
Leave the protective cardboard and film wrapping on the substa-
tion during moving and installation.
7.2 Moving substation to the installation place
The substations can be moved to the installation place using sev-
eral different ways, depending on the installation place and how to
get there.
We recommend that the substation is moved as close to the instal-
lation place as possible, using a pallet truck.
Plan the most convenient route to the installation place. Be aware
not to break floor and wall surfaces, stairs, doorposts etc.
The substation includes delicate components.
7.3 Removing the substation from the pallet
The substation is screwed on a mounting frame, which is screwed
on the pallet.
Loosen the screws pointed with a circle in the photo to your right
and lift the substation off the frame.
7.4 Lifting the substation
The substations can be lifted up by using straps, fitted around the
pipes, as shown on the photoes to your right, or it can be lifted by
hand in the pipes and fixed to a solid wall with two strong bolts,
screws or expansion plugs.
The substation must be installed and connected by authorized
service personnel only.
Installation must be in compliance with the local standards and
regulations.
Allow for adequate space around the substation for mounting
and maintenance purposes.
Do not hurt yourself or damage the
substation when lifting it!