Cable

To remove a cable, follow these steps:

Note: 

Loosen cable gland nut to set the cable free.

 

Loosen fastener nut to remove the gland with cable.

1. 

Disconnect power to the display. 

2. 

Loosen the cable gland nut and fastener nut on the outside of the box. 

Refer to 

Figure 77

.

Figure 77: 

Loosen Cable Gland Nut and Fastener Nut

FASTENER NUT

CABLE GLAND NUT

3. 

Apply the cable gland removal tool to wrap the cable gland in the 

fitting angle, and push all the way to the bottom. Refer to

 Figure 78

. The 

cable can be pulled out for a distance when necessary by loosening 

the cable gland nut. 

Figure 78: 

Apply Cable Gland Removal Tool

4. 

Remove the connector of the power cable and signal cable from the 

hub board. Refer to 

Figure 68 

and

 Figure 69.

5. 

Use the removal tool to rotate the cable gland 90° so the notches are 

aligned with the box. Refer to 

Figure 79

Figure 79: 

Rotate Cable Gland with Removal Tool

6. 

Remove 

cable gland removal tool

. Refer to 

Figure 80.

Figure 80: 

Remove Cable Gland Removal Tool

7. 

Cable gland is now loosened, pull the cable from below to 

remove the gland and cable out of the box. Refer to 

Figure 81

.

Figure 81: 

Remove Cable

Reverse these steps to install the cable.

Note: 

Properly re-install the cable and cable glands to make sure 

water does not get into the box.

Summary of Contents for DVX-1200 Series

Page 1: ...d to the top panel of the frame Refer to Figure 4 If the value at the bottom of the structure exceeds 1 mm for each 1 m of the frame s height adjust the structure or plan ahead for panel adjustments w...

Page 2: ...ve the C clamp after installing at least two bolts through the clip angles into the structure two bolts on each side Refer to Figure 13 6 Verify the alignment of the first row Repeat Step 5 if needed...

Page 3: ...jack in the first panel Refer to the contract specific Riser Diagram Note The maximum cable distance from the sending box to the first receiver card is 328 08 100 m For installations exceeding this d...

Page 4: ...Push lock up to open Refer to Figure 35 5 Remove the connector from the rear of the module Refer to Figure 36 Figure 35 Remove Both Connector Locks 6 Before reconnecting the modules check the module m...

Page 5: ...1 Disconnect power to the display 2 Remove the module s Refer to Front Access Module Removal p 4 To access the power box from the front the top row of modules Top Left Top Center and Top Right in Figu...

Page 6: ...ing these steps 1 Disconnect power to the display 2 Remove the backsheet Refer to Figure 38 Figure 39 Figure 40 and Figure 41 3 Find the hinge stopper on the bottom of the power box and loosen the scr...

Page 7: ...screwdriver to remove the screws securing the hub board to the power box Refer to Figure 70 Figure 70 Remove Screws from Hub Board 8 Pull the hub board gently outward to remove it from the power box...

Page 8: ...d push all the way to the bottom Refer to Figure 78 The cable can be pulled out for a distance when necessary by loosening the cable gland nut Figure 78 Apply Cable Gland Removal Tool 4 Remove the con...

Page 9: ...Follow these steps to install a PLR 1 Remove the backsheet Refer to Figure 38 Figure 39 Figure 40 and Figure 41 2 Find the pre drilled holes on the bottom of the horizontal stiffener underneath the po...

Page 10: ...325 8766 5 Connect the signal cable end on the panel with the signal cable connector on the PLR board A female connector or male connector can be chosen according to site requirements Refer to the Ri...

Reviews: