5 Installation
Installation and operation manual
11
RXYLQ10~14T7Y1B*
VRV IV system air conditioner
4P543426-1 – 2018.07
729
≤613
≥929
≥
AB
AA
a
(mm)
Minimum foundation
a
Anchor point (4×)
HP
AA
AB
8~14
1076
1302
▪ Fasten the unit in place using four foundation bolts M12. It is best
to screw in the foundation bolts until their length remains 20 mm
above the foundation surface.
20 mm
NOTICE
▪ Prepare a water drainage channel around the
foundation to drain waste water from around the unit.
During heating operation and when the outdoor
temperatures are negative, the drained water from the
outdoor unit will freeze up. If the water drainage is not
taken care of, the area around the unit might be very
slippery.
▪ When installed in a corrosive environment, use a nut
with plastic washer (a) to protect the nut tightening part
from rust.
a
5.3
Connecting the refrigerant piping
5.3.1
To route the refrigerant piping
Installation of refrigerant piping is possible as front connection or
side connection (when taken out from the bottom) as shown in the
figure below.
a
b
c
a
Left-side connection
b
Front connection
c
Right-side connection
For side connections, the knockout hole on the bottom plate should
be removed:
c
b
a
a
Large knockout hole
b
Drill
c
Points for drilling
NOTICE
Precautions when making knockout holes:
▪ Avoid damaging the casing.
▪ After making the knockout holes, we recommend you
remove the burrs and paint the edges and areas
around the edges using repair paint to prevent rusting.
▪ When passing electrical wiring through the knockout
holes, wrap the wiring with protective tape to prevent
damage.
5.3.2
To connect the refrigerant piping to the
outdoor unit
NOTICE
▪ Be sure to use the supplied accessory pipes when
carrying out piping work in the field.
▪ Be sure that the field installed piping does not touch
other pipes, the bottom panel or side panel. Especially
for the bottom and side connection, be sure to protect
the piping with suitable insulation, to prevent it from
coming into contact with the casing.
Connect the stop valves to the field piping using the accessory pipes
supplied with the unit.
The connections to the branch kits are the responsibility of the
installer (field piping).
5.3.3
To connect the multi connection piping kit
NOTICE
Improper installation may lead to malfunction of the
outdoor unit.
▪ Install the joints horizontally, so that the caution label (a) attached
to the joint comes to the top.
▪ Do not tilt the joint more than 7.5° (see view A).
▪ Do not install the joint vertically (see view B).
a
a
A
B
7.5°
7.5°
a
Caution label
X
Not allowed
O
Allowed
▪ Make sure that the total length of the piping connected to the joint
is absolute straight for more than 500 mm. Only if a straight field
piping of more than 120 mm is connected, more than 500 mm of
straight section can be ensured.
Summary of Contents for VRV IV RXMLQ8T7Y1B Series
Page 37: ......
Page 38: ......
Page 39: ......
Page 40: ...4P543426 1 2018 07 Copyright 2018 Daikin 4P543426 1 0000000M...