Warranty Registration Form (Scroll)
www.DaikinApplied.com 139
IOM 1207-6 • TRAILBLAZER
®
MODEL AGZ CHILLERS
PRE START-UP CHECKLIST
Pre Start-Up Checklist, All NO checks require an explanation under "Description". Please check
YES
or
NO
A.
Is the unit free of visible shipping damage, corrosion or paint problems?
B.
Is unit
level and isolators
installed?
C.
Does the unit meet all location, installation and service clearances per IOM Bulletin?
D.
Are all
fan fastener nuts on the fans tights
?
E.
Does electrical service correspond to unit nameplate?
Nameplate: Volts
Hertz
Phase
YES
NO
F.
Has electrical service been checked for proper phasing at each circuit power terminal block?
G.
Has unit been properly grounded
and all field wiring confirmed to unit electrical specifications
?
H.
Has a fused disconnect and fuses or breaker been sized per product manual and installed per local code?
N
umber of conduits
Number of Wires
Wire Size
I.
Are all electrical power connections tight?
J. B
een operating for 24 hours prior to start-up?
K.
Does all field wiring conform to unit electrical specifications?
L.
Are all service and liquid line valves
per the IOMM
in correct position?
M.
Water Strainer installed? Brazed Plate Evaporator 0.063" (1.6mm) or smaller perforations
N.
Has a flow switch been installed per the IOM manual?
O.
Has the chill water circuit been cleaned, flushed, and water treatment confirmed?
P.
Does the chiller water piping conform to the IOM manual?
Q.
Are fans properly aligned and turn freely?
R.
Is wind impingement against the air-cooled condenser a consideration?
S.
Are the condenser coils coated?
Description of unit location with respect to building structures. Include measured distances.
Description:
2
of
8
www.DaikinApplied.com
SF-
20001
AGZ/AMZ Start-Up
8
/2020