Technical data

subset

  of  the  latest  technical  data  is  available  on  the  regional  Daikin  website  (publicly  accessible).  The 

full  set

  of  latest  technical  data  is

available on the Daikin Business Portal (authentication required).

7.1

Service space: Outdoor unit

Suction side

In the illustrations below, the service space at the suction side is based on 35°C DB and cooling operation. Foresee
more space in the following cases:

▪ When the suction side temperature regularly exceeds this temperature.

▪ When the heat load of the outdoor units is expected to regularly exceed the maximum operating capacity.

Discharge side

Take refrigerant piping work into account when positioning the units. If your layout does not match with any of the
layouts below, contact your dealer.

Single unit (

) | Single row of units (

)

Multiple rows of units (

)

Stacked units (max. 2 levels) (

)

See figure 1 on the inside of the front cover.

(1)

For better serviceability, use a distance ≥250 mm

A,B,C,D

Obstacles (walls/baffle plates)

E

Obstacle (roof)

a,b,c,d,e

Minimum service space between the unit and obstacles A, B, C, D and E

e

B

Maximum distance between the unit and the edge of obstacle E, in the direction of obstacle B

e

D

Maximum distance between the unit and the edge of obstacle E, in the direction of obstacle D

H

U

Height of the unit

H

B

,H

D

Height of obstacles B and D

1

Seal the bottom of the installation frame to prevent discharged air from flowing back to the suction side through the bottom of the unit.

2

Maximum two units can be installed.
Not allowed

See figure 2 on the inside of the front cover.

(1)

For better serviceability, use a distance ≥250 mm

See figure 3 on the inside of the front cover.

(1)

For better serviceability, use a distance ≥250 mm

A1=>A2

(A1) If there is danger of drainage dripping and freezing between the upper and lower units…
(A2) Then install a 

roof

 between the upper and lower units. Install the upper unit high enough above the lower unit to prevent ice buildup at the

upper unit's bottom plate.

B1=>B2

(B1) If there is no danger of drainage dripping and freezing between the upper and lower units…
(B2) Then it is not required to install a roof, but 

seal the gap

 between the upper and lower units to prevent discharged air from flowing back to the

suction side through the bottom of the unit.

7.2

Piping diagram: Outdoor unit

sv

LPS

HPS

A

B

Service port (with 5/16" flare)

Stop valve

Filter

Check valve

Muffler

Solenoid valve

PCB cooling

Capillary tube

Electronic expansion valve

4‑way valve

High pressure switch

LPS

Low pressure switch

Heat exchanger

Compressor

Distributor

Accumulator

A

Field piping (liquid: Ø9.5 mm pinched pipe)

B

Field piping (gas: Ø25.4 mm pinched pipe)

Heating

Cooling

Summary of Contents for Sky Air Advance Series

Page 1: ...Installation manual Sky Air Advance series English Installation manual Sky Air Advance series RZA200D7Y1B RZA250D7Y1B...

Page 2: ...HD HU 200 1000 1000 500 HD HU A B C 200 1 300 1000 A B C E 200 1 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 250 1500 300 1500 B D E HB HU 300 1000 1000 500 HU HB HU 300 1250 1000 50...

Page 3: ...6 17 Direktiver med senere ndringer Direktiv med f retagna ndringar Direktiver med foretatte endringer Direktiivej sellaisina kuin ne ovat muutettuina v platn m zn n Smjernice kako je izmijenjeno ir n...

Page 4: ...staava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplota TS...

Page 5: ...sioning 14 5 2 To perform a test run 15 5 3 Error codes when performing a test run 16 6 Disposal 16 7 Technical data 17 7 1 Service space Outdoor unit 17 7 2 Piping diagram Outdoor unit 17 7 3 Wiring...

Page 6: ...ance or an operating electric heater 3 1 1 Installation site requirements of the outdoor unit Mind the spacing guidelines See the Technical data chapter and the figures on the inside of the front cove...

Page 7: ...ze between the heat exchanger and the casing of the unit This might decrease the operating efficiency INFORMATION We suggest to install the optional bottom plate heater EKBPH250D7 when the unit is ins...

Page 8: ...tation of the bends NOTICE Always protect the surrounding surfaces e g wiring insulation foam from heat when brazing 6 Do the following Insulate the liquid piping a and the gas piping b Wind heat insu...

Page 9: ...copper flare 4 3 3 To perform vacuum drying To remove all moisture from the system proceed as follows 1 Check that with the vacuum pump turned off the target vacuum is maintained for at least 1 hour 4...

Page 10: ...the refrigerant This product contains fluorinated greenhouse gases Do NOT vent gases into the atmosphere Refrigerant type R32 Global warming potential GWP value 675 WARNING FLAMMABLE MATERIAL The refr...

Page 11: ...70 R1 0 45 0 9 1 35 1 8 2 25 2 7 3 15 Standard liquid pipe size Length m 0 10 10 20 20 30 30 40 40 50 50 60 60 70 R2 0 2 0 4 0 6 0 8 1 1 2 1 4 Size up liquid pipe size Length m 0 5 5 10 10 15 15 20 20...

Page 12: ...refrigerant WARNING Only use R32 as refrigerant Other substances may cause explosions and accidents R32 contains fluorinated greenhouse gases Its global warming potential GWP value is 675 Do NOT vent...

Page 13: ...18 6 A 19 9 A Voltage range 380 415 V Phase 3N Frequency 50 Hz Wire sizes Must comply with applicable legislation Interconnection cables H05VV U4G2 5 Recommended field fuse 20 A Earth leakage circuit...

Page 14: ...ck the insulation resistance of the compressor NOTICE If after installation refrigerant accumulates in the compressor the insulation resistance over the poles can drop but if it is at least 1 M then t...

Page 15: ...e lit For any other action it needs to be lit first The backlight is lit for 30 seconds when you press a button 1 Perform introductory steps Action 1 Open the liquid stop valve and gas stop valve by r...

Page 16: ...ase of three phase power supply units Note Operation will be impossible Turn OFF the power recheck the wiring and switch two of the three electrical wires L4 The air inlet or air outlet is blocked U0...

Page 17: ...m distance between the unit and the edge of obstacle E in the direction of obstacle D HU Height of the unit HB HD Height of obstacles B and D 1 Seal the bottom of the installation frame to prevent dis...

Page 18: ...d Legend Optional Optional Part n Part n Description Description A1P Printed circuit board main A2P Printed circuit board noise filter A3P Printed circuit board inverter A4P Printed circuit board fan...

Page 19: ......

Page 20: ...4P573384 1 2019 04 Copyright 2019 Daikin 4P573384 1 0000000S...

Reviews: