5 Commissioning

Installation manual

10

RZQG7 RZQG71~12 RZQG140L7Y1L

Split system air conditioners

4P473073-1 – 2017.03

5

Commissioning

NOTICE

NEVER  operate  the  unit  without  thermistors  and/or
pressure  sensors/switches.  Burning  of  the  compressor
might result.

5.1

Checklist before commissioning

Do NOT operate the system before the following checks are OK:

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between the outdoor unit and the indoor unit

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed  according  to  this  document,  and  have  not  been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

5.2

To perform a test run

This task is only applicable when using the BRC1E52 user interface.

▪ When  using  BRC1E51,  see  the  installation  manual  of  the  user

interface.

▪ When using BRC1D, see the service manual of the user interface.

NOTICE

Do not interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve (A) and gas stop valve (B)
by removing the stem cap and turning
counterclockwise with a hex wrench until it stops.

A

B

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run.

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

2

Press at least 4 seconds.

The Service Settings menu
is displayed.

3

Select Test Operation.

Return

Setting

Service Settings                   1/3

Test Operation

Maintenance Contact

Field Settings

Demand

Min Setpoints Differential

Group Address

4

Press.

Test Operation is
displayed on the home
menu.

Cool

Return

Setting

Test Operation

5

Press within 10 seconds.

Test run starts.

Summary of Contents for RZQG71L8Y1L

Page 1: ...Installation manual Split system air conditioners English Installation manual Split system air conditioners RZQG71L9V1L RZQG71L8Y1L RZQG100L8Y1L RZQG125L8Y1L RZQG140L7Y1L...

Page 2: ...500 HU HD HU 200 1000 1000 500 HD HU HU a b 100 100 c d e eB eD A B C D E HB HD A B C 200 300 1000 A B C E 200 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300...

Page 3: ...sor 9 5 Commissioning 10 5 1 Checklist before commissioning 10 5 2 To perform a test run 10 5 3 Error codes when performing a test run 11 6 Technical data 12 6 1 Service space Outdoor unit 12 6 2 Pipi...

Page 4: ...5 3 5 5 4 M12 a a Make sure not to cover the drain holes INFORMATION The recommended height of the upper protruding part of the bolts is 20 mm 20 NOTICE Fix the outdoor unit to the foundation bolts us...

Page 5: ...piping to the outdoor unit 1 Do the following Remove the service cover a with screw b Remove the piping intake plate c with screw d c a b d 2 Choose a piping route a b c or d a b c d 3 If you have cho...

Page 6: ...plate NOTICE Make sure to use a recommended bubble test solution from your wholesaler Do not use soap water which may cause cracking of flare nuts soap water may contain salt which absorbs moisture t...

Page 7: ...g refrigerant piping Setup on page 6 4 4 4 To charge refrigerant WARNING Only use R410A as refrigerant Other substances may cause explosions and accidents R410A contains fluorinated greenhouse gases I...

Page 8: ...circuit power Ssc greater than or equal to the minimum Ssc value Model Minimum Ssc value RZQG71_V1 RZQG100 140_Y1 1170 kVA 4 5 2 Specifications of standard wiring components Component V1 Y1 71 71 100...

Page 9: ...6 Finishing the outdoor unit installation 4 6 1 To finish the outdoor unit installation 1 Insulate and fix the refrigerant piping and interconnection cable as follows f b a e d c a Gas pipe b Gas pipe...

Page 10: ...nts or squeezed pipes on the inside of the indoor and outdoor units There are NO refrigerant leaks The correct pipe size is installed and the pipes are properly insulated The stop valves gas and liqui...

Page 11: ...rrently set temperature is not displayed The wiring is disconnected or there is a wiring error between power supply and outdoor unit between outdoor unit and indoor units between indoor unit and user...

Page 12: ...discharged air from flowing back to the suction side through the bottom of the unit 2 Maximum two units can be installed Not allowed Multiple rows of units See figure 2 on the inside of the front cov...

Page 13: ...citor DS1 DIP switch F1U F8U RZQG71_V1 F1U F2U Fuse F6U Fuse T 3 15 A 250 V F7U F8U Fuse F 1 0 A 250 V F1U F8U RZQG_Y1 F1U F2U Fuse 31 5 A 250 V F1U A2P Fuse T 5 0 A 250 V F3U F6U Fuse T 6 3 A 250 V F...

Page 14: ......

Page 15: ......

Page 16: ...4P473073 1 2017 03 Copyright 2017 Daikin...

Reviews: