Installation manual

18

RXYSQ6TAV1B

VRV IV-S System air conditioner

4P482260-1 – 2017.03

This unit uses an inverter, and therefore generates noise, which
will have to be reduced to avoid interfering with other devices.
The outer casing of the product may take on an electrical charge
due to leaked electrical current, which will have to be discharged
with the grounding.

Only for Y1: Make sure to connect power supply cables in
normal phase. If connected in reverse phase, the remote
controller of the indoor unit indicates "

U1

" and the equipment

cannot operate. Change any two of the three power supply
cables (L1, L2, L3) to correct phase.

10.3. Connection example of total system wiring 

For Sky Air or room air conditioner indoor units only: see 

figure 9

For VRV indoor units only: see 

figure 10

10.4. Connecting power wire and transmission wires

Let the power wire (including ground wire) go through the power
outlet port on either the front, side or back of the outdoor unit.

Let the transmission wires go through the cable outlet port, pipe
outlet port or knock-out hole on either the front, side or back of
the outdoor unit. 

(See figure 12)

.

Precautions when knocking out knock-out holes

To punch a knock hole, hit on it with a hammer.

After knocking out the holes, we recommend you paint the
edges and areas around the edges using the repair paint to
prevent rusting.

When passing electrical wiring through the knock holes, remove
any burrs from the knock holes and wrap the wiring with
protective tape to prevent damage.

If there is any possibility that small animals enter the system
through the knock holes, plug the holes with packing materials
(to be prepared on-site).

10.5. Power circuit and cable requirements

A power circuit (see table below) must be provided for connection of
the unit. This circuit must be protected with the required safety
devices, i.e. a main switch, a slow blow fuse on the phase and an
earth leakage breaker.

When installing the earth leakage breaker make sure that it is
compatible with the inverter (resistant to high frequency
electrical noise) to avoid unnecessary opening of the earth
leakage breaker.

In connecting the power cable to the power terminal block,
securely clamp the cable as shown in 

figure 12

.

1

Power

2

Earth leakage breaker

3

Branch switch overcurrent breaker (fuse)

4

Ground

5

BP unit

1

Power

2

Earth leakage breaker

3

Branch switch overcurrent breaker (fuse)

4

Ground

5

Remote controller

A

Rear direction

B

Lateral direction

C

Front direction

1

Power terminal block (X1M)

2

Control wiring between units

3

Power cable with ground wire. (Keep proper distance between 
power cable and control wiring).

4

Clamp (field supply)

5

Stop valve mounting plate

6

Power cable

7

Ground cable (yellow/green). Make sure that the ground cable 
length is longer than the power cable length. This is to make sure 
that the ground cable is loosing last in case of pulling.

8

Fix the control wiring with the clamp

9

Control terminal block (X2M)

1

Knock-out hole

2

Burr

3

Packing materials

Use a power wire pipe for the power wiring.

Outside the unit, make sure the low voltage electric
wiring (i.e. for the remote control, between units, etc.)
and the high voltage electric wiring do not pass near
each other, keeping them at least 50 mm apart.
Proximity may cause electrical interference,
malfunctions, and breakage.

Be sure to connect the power wiring to the power
wiring terminal block and secure it as described under

"10.4. Connecting power wire and transmission wires"
on page 18

.

Inter-unit wiring should be secured as described in

"10.4. Connecting power wire and transmission wires"
on page 18

.

Secure the wiring with clamps so that it does not
touch the piping.

Make sure the wiring and the electric box lid do not
stick up above the structure, and close the cover
firmly.

RXYSQ_V1

Phase and frequency

1~ 50 Hz

Voltage

220-240 V

Recommended field fuse

32 A

Minimum circuit amps 
(MCA)

(*)

(*)

Stated values are maximum values (see electrical data of combination with 
indoor units for exact values).

27

Transmission line section

0.75~1.25 mm

2

Wire type

(†)

(†) Only in protected pipes, use H07RN-F when protected pipes are not used.

H05VV

NOTE

Select the power supply cable in accordance with
relevant local and national regulations.

Wire size must comply with the applicable local
and national code.

Specifications for local wiring power cord and
branch wiring are in compliance with IEC60245.

After finishing the electric work, confirm that each electric
part and terminal inside the electric parts box is connected
securely.

2

3

1

4PEN482260-1.book  Page 18  Monday, March 20, 2017  8:54 PM

Summary of Contents for RXYSQ-TAV

Page 1: ...INSTALLATION MANUAL RXYSQ6TAV1B VRV IV S System air conditioner 4PEN482260 1 book Page 1 Monday March 20 2017 8 54 PM...

Page 2: ...L1 H 0 L2 1 2 H 1 2 H L2 H L2 H L2 H L2 H L2 H L2 H L2 H 150 500 500 500 500 750 100 100 100 100 200 300 200 100 250 250 500 1000 1000 1000 500 500 500 500 1000 1000 1000 1000 500 500 1000 500 1000 1...

Page 3: ...2 3 4 1 2 3 4 380 415 V V1 Y1 10 16 V 230 V 230 V 16 V 16 V 16 V 1 2 3 2 3 4 1 2 3 4 1 4 5 5 5 380 415 V V1 Y1 11 2 1 1 1 2 3 4 4 V1 1 50 Hz Y1 3N 50 Hz 1 50 Hz 1 8 11 9 8 10 4PEN482260 1 book Page 1...

Page 4: ...B C 08 Nota tal como estabelecido em A e com o parecer positivo de B de acordo com o Certificado C 09 A B C 10 Bem rk som anf rt i A og positivt vurderet af B i henhold til Certifikat C 11 Information...

Page 5: ...The English text is the original instruction Other languages are translations of the original instructions 1 SAFETY CONSIDERATIONS The precautions listed here are divided into the following two types...

Page 6: ...tubes are not effective grounds Lightning conductor or telephone ground wire Electric potential may rise abnormally if struck by a lightning bolt Be sure to install an earth leakage breaker Failure to...

Page 7: ...an optimum refrigerant branching kit refer to Refrigerant branch kit selection on page 11 2 5 Technical and electrical specifications Refer to the Engineering Data Book for the complete list of specif...

Page 8: ...e satisfied and that meets with your customer s approval Places which are well ventilated Places where the unit does not bother next door neighbours Safe places which can withstand the unit s weight a...

Page 9: ...evention of falling over If it is necessary to prevent the unit from falling over install as shown in the figure prepare all 4 wires as indicated in the drawing unscrew the top plate at the 4 location...

Page 10: ...H A and L is shown in the table below NOTE If drain holes of the outdoor unit are covered by a mounting base or by floor surface raise the unit in order to provide a free space of more than 100 mm und...

Page 11: ...reat caution is needed when passing copper tubes through walls For handling of stop valves refer to 9 3 How to use the stop valve on page 9 Only use the flare nuts included with the unit Using differe...

Page 12: ...material field supply to stop up all gaps as shown in the figure Insects or small animals entering the outdoor unit may cause a short circuit in the electrical box Pipe size Tightening torque N m A m...

Page 13: ...ul not to let the BP unit and outdoor branch piping come into contact with the compressor terminal cover If the liquid side piping insulation might come into contact with it adjust the height as shown...

Page 14: ...al cover 3 For Sky Air or room air conditioner indoor units only BP unit and outdoor field piping 3 For VRV indoor units only Indoor and outdoor field piping 4 Corking etc 5 Insulation material field...

Page 15: ...Difference in height Difference in height between outdoor and indoor units H1 30 m Between outdoor and BP units Difference in height Difference in height between outdoor and BP units H2 30 m Between...

Page 16: ...c d e Total indoor capacity Q Gas pipe Liquid pipe Qc Qd Qe 5 0 kW 12 7x0 8 6 4x0 8 Qc Qd Qe 5 0 kW 15 9x1 0 9 5x0 8 NOTE Qc Qd Qe is total connected indoor capacity c d e indicates the symbols in th...

Page 17: ...If the recommended pipe size is not available stick to the original pipe diameter which may result in a small capacity decrease Gas side RXYSQ4 5 15 9 19 1 RXYSQ6 19 1 22 2 A Piping between outdoor un...

Page 18: ...tory charged with refrigerant and depending on pipe sizes and pipe lengths some systems require additional charging of refrigerant See How to calculate the additional refrigerant to be charged on page...

Page 19: ...ollows 1 Turn on the power of the outdoor unit 2 Press at least 5 seconds 3 Press 51 times on 4 Press once 5 Press once 6 Press 2 times on The setting for changing from VRV applications to Sky Air or...

Page 20: ...eration stops The operation automatically stops within 30 minutes If the refrigerant charge cannot be finished within 30 minutes repeat step 5 If the operation stops immediately after restart there is...

Page 21: ...in switch has a contact separation of at least 3 mm in all poles Never squeeze bundled cables into a unit Fix cables so that cables do not make contact with the pipes especially on high pressure side...

Page 22: ...urely clamp the cable as shown in figure 12 1 Power 2 Earth leakage breaker 3 Branch switch overcurrent breaker fuse 4 Ground 5 BP unit 1 Power 2 Earth leakage breaker 3 Branch switch overcurrent brea...

Page 23: ...vent outside pressure being exerted on the terminal board Use an appropriate screwdriver for tightening the terminal screws A screwdriver with a small head will strip the head and make proper tighteni...

Page 24: ...nd transmission wiring Use a designated power supply and transmission wiring and make sure that it has been carried out according to the instructions described in this manual according to the wiring d...

Page 25: ...BS1 BS5 3 DIP switches 2 DS1 1 DS1 2 x OFF w ON c blinking For changing the set mode For field setting For field setting For test operation For resetting the address when the wiring is changed or whe...

Page 26: ...ic judgement of piping length 4 After the test operation maximum 30 minutes the unit automatically stops Check the operation results by the outdoor unit led indication H1P H2P H3P H4P H5P H6P H7P OFF...

Page 27: ...mmediately and then energize the heater for a sufficient length of time before restarting the operation Run each indoor unit one at a time and make sure the corresponding outdoor unit is also running...

Page 28: ...y against leakage according to local regulations or standards The following standards may be applicable if local regulations are not available This unit like other air conditioning systems uses R410A...

Page 29: ...tional legislation amount of refrigerant in a single unit system amount of refrigerant with which the system is charged before leaving the factory additional charging amount amount of refrigerant adde...

Page 30: ...4PEN482260 1 book Page 1 Monday March 20 2017 8 54 PM...

Page 31: ...E E E E E 12 A B C 2 2 3 2 4 7 2 9 3 2 3 5 6 1 4 8 3 2 4 3 2 1 6 8 9 7 2 V1 Y1 3 14 A1P A2P A4P X2M X2M F1 F1 F2 F2 TO IN D UNIT C H SELECTOR X2M A C B A4P TO OUT D UNIT F1 F1 F2 A C B F2 TO IN D UNIT...

Page 32: ...4P482260 1 2017 03 Copyright 2017 Daikin 4PEN482260 1 book Page 1 Monday March 20 2017 8 54 PM...

Reviews: