CAUTION

When connecting the connection wires to the terminal board using a single core 
wire, be sure to perform curling. 
Problems with the work may cause heat and fires.  

3) Pull the wire and make sure that it does not disconnect. Then fix the wire in place with a wire stop.

Test Run and Final Check

1.

Trial Operation and Testing.

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

For Heat pump

• In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable temperature.

1) Trial operation may be disabled in either mode depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26C

°

 to 28

°

C in cooling mode, 20

°

C to 24

°

C in 

heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

For Cooling only

• Select the lowest programmable temperature.

1) Trial operation in cooling mode may be disabled depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26

°

C to 28

°

C).

3) For protection, the unit disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the Operation Manual to ensure that all functions and parts, 

such as louver movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again.

2.

Test Items.

Test Items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

The specified wires are used for interconnecting wire connections.

Inoperative or burn damage

Indoor or outdoor unit’s air intake or exhaust has clear path of air.
Shut-off valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

z

 Stripping wire at terminal block

01_EN_3P159684-2F.fm  Page 10  Wednesday, December 7, 2005  3:18 PM

Summary of Contents for RXS50E2V1B

Page 1: ...rlands Espa ol Italiano Portugues T rk e English Montaj k lavuzlar R410A Split serisi Installation manual R410A Split series Installationsanleitung Split Baureihe R410A Manuel d installation S rie spl...

Page 2: ...n TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951...

Page 3: ...cause terminal overheating electrical shock or fire If any refrigerant has leaked out during the installation work ventilate the room The refrigerant produces a toxic gas if exposed to flames After al...

Page 4: ...n if they are more than 3 meter away depending on radio wave conditions 8 In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten the life of the air conditioner 9...

Page 5: ...centres 330m m Allow space for piping and electrical servicing 250mm from wall CAUTION Set the piping length from 1 5m to 30m Wrap the insulation pipe with the finishing tape from bottom to top Stop...

Page 6: ...om the foundation surface Outdoor Unit Installation 1 Installing Outdoor Unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawi...

Page 7: ...enches Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and escaping gas 2 To prevent gas leakage apply refrigeration machine oil on both inner and outer surfaces...

Page 8: ...gauge manifold to gas shut off valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no ope...

Page 9: ...aterial Polyethylene foam Heat transfer rate 0 041 to 0 052W mK 0 035 to 0 045kcal mh C Refrigerant gas pipe s surface temperature reaches 110 C max Choose heat insulation materials that will withstan...

Page 10: ...residence or office the space where there is a human 1 You can expand the operation range to 15 C by turning on switch B SW4 on the PCB If the outdoor temperature falls to 20 C or lower the operation...

Page 11: ...rews Observe the notes mentioned following when wiring to the power supply terminal board Precautions to be taken for power supply wiring Use a round crimp style terminal for connection to the power s...

Page 12: ...el 26 C to 28 C 3 For protection the unit disables restart operation for 3 minutes after it is turned off 1 3 Carry out the test operation in accordance with the Operation Manual to ensure that all fu...

Page 13: ...0601 HT 3P159684 2F M05B071A...

Reviews: