5.

Purging Air and Checking Gas Leakage

• When piping work is completed, it is necessary to purge the air and check for gas leakage.

WARNING

1) Do not mix any substance other than the specified refrigerant (R410A) into the refrigeration cycle.
2) When refrigerant gas leaks occur, ventilate the room as soon and as much as possible.
3) R410A, as well as other refrigerants, should always be recovered and never be released directly into the environment.
4) Use a vacuum pump for R410A exclusively. Using the same vacuum pump for different refrigerants may damage the vacuum 

pump or the unit.

• If using additional refrigerant, perform air purging from the refrigerant pipes and 

indoor unit using a vacuum pump, then charge additional refrigerant.

• Use a hexagonal wrench (4mm) to operate the shut-off valve rod.
• All refrigerant pipe joints should be tightened with a torque wrench at the specified 

tightening torque.

*1. Pipe length vs. vacuum pump run time

*2. If the compound pressure gauge pointer swings back, refrigerant may have water content or a loose pipe joint may exists.  

Check all pipe joints and retighten nuts as needed, then repeat steps 2) through 4).

1) Connect projection side (on which worm pin is pressed) of charging hose (which comes from gauge manifold) to gas shut-off 

valve’s service port.

2) Fully open gauge manifold’s low-pressure valve (Lo) and completely close its high-pressure valve (Hi).  

(High-pressure valve subsequently requires no operation.)

3)  Do vacuum pumping and make sure that the compound pressure gauge reads –0.1MPa (–76cmHg)*1.

4) Close gauge manifold’s low-pressure valve (Lo) and stop vacuum pump.  

(Keep this state for a few minutes to make sure that the compound pressure gauge pointer does not swing back.)*2.

5) Remove covers from liquid shut-off value and gas shut-off valve.

6) Turn the liquid shut-off valve’s rod 90 degrees counterclockwise with a hexagonal wrench to open valve.

Close it after 5 seconds, and check for gas leakage.
Using soapy water, check for gas leakage from indoor unit’s flare and outdoor unit’s flare and valve rods.
After the check is complete, wipe all soapy water off.

7) Disconnect charging hose from gas shut-off valve’s service port, then fully open liquid and gas shut-off valves.

(Do not attempt to turn valve rod beyond its stop.)

8) Tighten valve lids and service port caps for the liquid and gas shut-off valves with a torque wrench at the specified torques.

Pipe length

Up to 15 metres

More than 15 metres

Run time

Not less than 10 min.

Not less than 15 min.

Gauge 
manifold

Compound 
pressure gauge

Pressure meter

Low-pressure 
valve

High-pressure 
valve

Charging 
hoses

Vacuum pump

Valve lids

Service port

Liquid 
shut-off 
valve

Gas 
shut-off 
valve

01_EN_3P159684-2F.fm  Page 6  Wednesday, December 7, 2005  3:18 PM

Summary of Contents for RXS50E2V1B

Page 1: ...rlands Espa ol Italiano Portugues T rk e English Montaj k lavuzlar R410A Split serisi Installation manual R410A Split series Installationsanleitung Split Baureihe R410A Manuel d installation S rie spl...

Page 2: ...n TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951 KRQ ECMC99 4476 Daikin TCF 020 95951...

Page 3: ...cause terminal overheating electrical shock or fire If any refrigerant has leaked out during the installation work ventilate the room The refrigerant produces a toxic gas if exposed to flames After al...

Page 4: ...n if they are more than 3 meter away depending on radio wave conditions 8 In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten the life of the air conditioner 9...

Page 5: ...centres 330m m Allow space for piping and electrical servicing 250mm from wall CAUTION Set the piping length from 1 5m to 30m Wrap the insulation pipe with the finishing tape from bottom to top Stop...

Page 6: ...om the foundation surface Outdoor Unit Installation 1 Installing Outdoor Unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawi...

Page 7: ...enches Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and escaping gas 2 To prevent gas leakage apply refrigeration machine oil on both inner and outer surfaces...

Page 8: ...gauge manifold to gas shut off valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no ope...

Page 9: ...aterial Polyethylene foam Heat transfer rate 0 041 to 0 052W mK 0 035 to 0 045kcal mh C Refrigerant gas pipe s surface temperature reaches 110 C max Choose heat insulation materials that will withstan...

Page 10: ...residence or office the space where there is a human 1 You can expand the operation range to 15 C by turning on switch B SW4 on the PCB If the outdoor temperature falls to 20 C or lower the operation...

Page 11: ...rews Observe the notes mentioned following when wiring to the power supply terminal board Precautions to be taken for power supply wiring Use a round crimp style terminal for connection to the power s...

Page 12: ...el 26 C to 28 C 3 For protection the unit disables restart operation for 3 minutes after it is turned off 1 3 Carry out the test operation in accordance with the Operation Manual to ensure that all fu...

Page 13: ...0601 HT 3P159684 2F M05B071A...