Remove the blind cap from the gas line stop valve (7) and the
liquid line stop valve (8).

13

Loosen the gland packing retainers of the gas line stop valve (7)
and the liquid line stop valve (8) using a hexagon wrench.

14

Partially open the gas line stop valve and the liquid line stop
valve and wait until the pressure indicated by the low pressure
gauge pointer equals the pressure indicated by the high
pressure gauge pointer.

15

Fully open the gas line stop valve and the liquid line stop valve.

16

Remove the R22 cylinder and the vacuum pump from the gauge
manifold.

17

Remove the hoses between the gauge manifold and the
condensing unit.

18

Check the stop valves for leakage.

Piping insulation

After finishing the leak test and vacuum drying, the piping must be
insulated to prevent reduction of the cooling capacity. Take into
account the following points when insulating the piping:

1.

Provide a separate insulation for the gas line piping and the
liquid line piping.

2.

Thoroughly insulate around the pipe connections.

3.

Use Armaflex material with a thickness of 9 mm.

F

IELD

 

WIRING

Parts table

Power circuit and cable requirements

A power circuit (see table below) must be provided for connection of
the condensing unit. This circuit must be protected with the required
safety devices, i.e. a circuit breaker, a slow blow fuse on each phase
and an earth leak detector.

CENELEC system for cable designation

All field wiring and components must be installed by a
licensed electrician and must comply with relevant
European and national regulations.

The field wiring must be carried out in accordance
with the wiring diagrams (see 

figure 6

figure 7

  and

figure 8

) and the instructions given below.

Be sure to use a dedicated power circuit. Never use a
power supply shared by another appliance.

: Earth connection

L1, L2, L3

: Live line

N

: Neutral

1

: Power supply panel

2

: Switch box condensing unit

F2,3,4U

: Field fuses

S3S

: Main isolator switch

: Earth leak detector

Model

Phase and 

frequency

Voltage

Recommended 

fuses

Cable type 

(CENELEC Code)

ER3DAT1

3~50 Hz

220V

16 aM

H07RN-F4G2.5

ER3DAV1

1~50 Hz

220-240V

25 aM

H07RN-F3G4

ER3DAW1

3N~50 Hz

380-415V

10 aM

H07RN-F5G2.5

ER5DAT1

3~50 Hz

220V

20 aM

H07RN-F4G2.5

ER5DAW1

3N~50 Hz

380-415V

16 aM

H07RN-F5G2.5

ER8DAT1

3~50 Hz

220V

32 aM

H07RN-F4G6

ER8DAW1

3N~50 Hz

380-415V

25 aM

H07RN-F5G4

ER10DAT1

3~50 Hz

220V

40 aM

H07RN-F4G10

ER10DAW1

3N~50 Hz

380-415V

25 aM

H07RN-F5G4

H

Harmonised cable type

07

450/750 volts

V

PVC wire insulation

R

Vulcanised natural rubber wire insulation

V

PVC conductor insulation

N

Neoprene conductor insulation

U

Solid core

F

Flexible core conductor

4

Number of conductors

G

One conductor is the earth conductor (yellow/green)

X

No earth conductor (yellow/green)

1.5

Cross-section of conductors (mm

2

)

Switch off the power circuit before making any connections
(switch off the circuit breaker, remove or switch off the
fuses).

Always use the cable indicated in the above table.

Remove maximum 8 mm of the PVC wire insulation when
connecting the wires to the terminals. To connect a wire,
depress the clamp spring using a screwdriver, insert the
wire and then remove the screwdriver (see figure). To
remove a wire, proceed in reverse order.

Summary of Contents for ER10DAT1

Page 1: ...INSTALLATION MANUAL ER3DAW1 ER3DAT1 ER3DAV1 ER5DAW1 ER5DAT1 ER8DAW1 ER8DAT1 ER10DAW1 ER10DAT1 Air cooled condensing units...

Page 2: ...1464 15 ER10DA mm 1390 1021 375 30 1560 294 371 39 1434 1464 15 3 3 DAIKIN F D A B E C A B C D E F ER3DA mm 800 500 1075 300 800 1055 ER5DA mm 800 500 1075 300 800 1055 ER8DA mm 800 500 1170 300 800...

Page 3: ...ons can be purchased to allow easier installation MAIN COMPONENTS refer to figure 1 ER3DA ER5DA ER8DA ER10DA Air cooled condensing units Installation manual IMPROPER INSTALLATION OR ATTACHMENT OF EQUI...

Page 4: ...standing supports Attach the unit to the supports using the bolts spring lock washers and nuts provided with the kit 4 Level the unit in both directions 5 Use four anchor bolts with M8 thread to fix t...

Page 5: ...rom the gauge manifold 20 Remove the blind cap from the gas line stop valve 11 and the liquid line stop valve 12 21 Loosen the gland packing retainers of the gas line stop valve 11 and the liquid line...

Page 6: ...licensed electrician and must comply with relevant European and national regulations The field wiring must be carried out in accordance with the wiring diagrams see figure 6 figure 7 and figure 8 and...

Page 7: ...it and the switch box of the air conditioning unit The cable must be of the type H05VV U5X1 5 and must be connected to terminals 1 3 4 5 and 6 of the condensing unit as shown on the wiring diagrams se...

Page 8: ...NOTES NOTES...

Page 9: ...eration of the air conditioning system is then controlled by the remote control Shut down by switching off the remote control and the circuit breaker of the power circuit WARNINGS Emergency shut down...

Page 10: ...NOTES...

Page 11: ...NOTES...

Page 12: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PWEN00410 1C...

Reviews: