6 Preparation
Installation manual
5
DCC601A51
intelligent Tablet Controller
4P414342-1D – 2020.12
5.4.2
Daikin-supplied tablet (ASUS ZenPad 8.0
Z380M)
If you choose the local function mode you have to use a Daikin-
supplied tablet to run the intelligent Tablet Controller app.
The intelligent Tablet Controller app can be installed from Google
Play.
6
Preparation
6.1
Before installation
Before you start installing the intelligent Tablet Controller, complete
the following preparations:
▪ Check that the intelligent Tablet Controller kit comes with all
accessories, see
▪ Check that you have all equipment necessary to install the
intelligent Tablet Controller kit modules, see
5].
▪ Check that an appropriate space for installing the intelligent Tablet
Controller modules is available, see
▪ Familiarise yourself with the location of the terminals and switches
of the intelligent Tablet Controller modules, see
location of terminals and switches"
6].
6.2
Necessary equipment
Use the following equipment to install the intelligent Tablet Controller
kit modules:
▪ A flat-blade screwdriver
▪ A Phillips screwdriver
▪ The necessary amount of electrical wires and appropriate wiring
tools. For more info on what wires to use, see
7].
6.3
Determining installation place
Make sure to install the intelligent Tablet Controller components in a
place that complies with the conditions described in the following
sections.
6.3.1
About installation place and mounting
direction
Make sure the installation place complies with the following
requirements:
▪ Location: Indoor, inside an electrical cabinet.
▪ The electrical cabinet:
▪ must be lockable or designed to be opened only with a special
tool. The key or tool should be available only to service
personnel.
▪ must be installed in a space with no access for the general
public.
▪ must comply with the applicable legislation.
▪ must have ingress protection class of IP4X or higher (however,
make sure enough ventilation is provided to prevent
overheating of the equipment).
▪ must have impact protection class of IK07 or higher (see
international standard IEC 62262‑2002).
▪ must have a minimum height of 290 mm and minimum width of
410 mm to allow for the clearance specified in
▪ Mounting direction: vertical only
▪ Make sure the installation place complies with the environmental
"10.1 Environmental conditions"
6.3.2
About required space
The following figure indicates the minimum space required for
installation.
▪ Make sure there is a minimum clearance of 60 mm between both
the CPU module, the I/O module and the wiring ducts and a
minimum clearance of 80 mm between the modules and the
electrical cabinet in the vertical direction.
▪ Make sure there is a minimum vertical clearance of 70 mm
between the WAGO PSU and the wiring ducts.
▪ The CPU module and I/O module can be installed without
clearance in the horizontal direction, but make sure there is a
minimum clearance of 20 mm between the modules and the
electrical cabinet.
▪ The WAGO PSU requires a minimum clearance of 15 mm on both
sides in the horizontal direction.
≥60
≥80
≥70
≥60
≥70
50
136
130
152
≥15
≥15
152
a
b
a
≥80
≥20
I/O
CPU
+ + - -
L N
(mm)
a
Wire duct
b
Electrical cabinet
Observe the depth of these modules and make sure you provide the
necessary amount of space in depth in the electrical cabinet.
Module
Depth
CPU module
45 mm
I/O module
39 mm
WAGO PSU
92 mm