background image

6 Commissioning

Installation manual

11

ATXM20~50+FTXM20~71N2V1B
Daikin room air conditioner
3P482320-8K – 2018.09

6

Commissioning

NOTICE

NEVER  operate  the  unit  without  thermistors  and/or
pressure  sensors/switches.  Burning  of  the  compressor
might result.

6.1

Checklist before commissioning

Do NOT operate the system before the following checks are OK:

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

The 

outdoor unit

 is properly mounted.

Air inlet/outlet

Check  that  the  air  inlet  and  outlet  of  the  unit  is  NOT
obstructed  by  paper  sheets,  cardboard,  or  any  other
material.

There are NO 

missing phases

 or 

reversed phases

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

Drainage

Make sure drainage flows smoothly.

Possible consequence: 

Condensate water might drip.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

The  specified  wires  are  used  for  the 

interconnection

cable

.

The indoor unit receives the signals of the 

user interface

.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

6.2

To perform a test run

Prerequisite: 

Power supply MUST be in the specified range.

Prerequisite: 

Test  run  may  be  performed  in  cooling  or  heating

mode.

Prerequisite: 

Test run should be performed in accordance with the

operation  manual  of  the  indoor  unit  to  make  sure  that  all  functions
and parts are working properly.

1

In  cooling  mode,  select  the  lowest  programmable  temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.

2

When  the  test  run  is  finished,  set  the  temperature  to  a  normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.

3

The  system  stops  operating  3  minutes  after  the  unit  is  turned
OFF.

6.2.1

To perform a test run using the user
interface

1

Press 

 to switch the system on.

2

Press 

 and 

 simultaneously.

3

Press 

, select 

and press 

.

Result: 

Test  run  operation  will  stop  automatically  after  about

30 minutes.

4

To stop operation sooner, press 

.

7

Disposal

NOTICE

Do  NOT  try  to  dismantle  the  system  yourself:  dismantling
of  the  system,  treatment  of  the  refrigerant,  oil  and  other
parts  MUST  comply  with  applicable  legislation.  Units
MUST  be  treated  at  a  specialised  treatment  facility  for
reuse, recycling and recovery.

Summary of Contents for CTXM15N2V1B

Page 1: ...in room air conditioner English Installation manual Daikin room air conditioner CTXM15N2V1B ATXM20N2V1B ATXM25N2V1B ATXM35N2V1B ATXM50N2V1B FTXM20N2V1B FTXM25N2V1B FTXM35N2V1B FTXM42N2V1B FTXM50N2V1B...

Page 2: ...sau alt e document e normativ e cu condi ia ca acestea s fie utilizate n conformitate cu instruc iunile noastre skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v sk...

Page 3: ...erence Target audience Authorised installers INFORMATION This appliance is intended to be used by expert or trained users in shops in light industry and on farms or for commercial and household use by...

Page 4: ...allation 5 1 Opening the indoor unit 5 1 1 To remove the front panel 1 Hold the front panel by the panel tabs on both sides and open it a a Panel tabs 2 Remove the front panel by sliding it to the lef...

Page 5: ...Finish the installation by securing the mounting plate on the wall using M4 25L screws field supply Class 15 42 Class 50 71 INFORMATION The removed pipe port cover can be kept in the mounting plate po...

Page 6: ...over as this would damage the front grille 5 2 4 To provide drainage Make sure condensation water can be evacuated properly This involves General guidelines Connecting the drain piping to the indoor u...

Page 7: ...drain leakage from the plug a a 4 mm hexagonal wrench 3 Insert the drain hose on the left side and do not forget to tighten it with the fixing screw otherwise water leakage may occur a b a b a Insulat...

Page 8: ...part from each other Transmission wiring and power supply wiring may cross but may NOT run parallel In order to avoid any electrical interference the distance between both wirings should ALWAYS be at...

Page 9: ...the definition of Directive 2014 53 EU INFORMATION Install the wireless LAN adapter after finishing the indoor unit installation Refer to 5 6 2 To install the wireless LAN adapter on page 9 Basic par...

Page 10: ...ssory 2 To place the wireless LAN adapter into the unit For class 15 42 1 Place the wireless LAN adapter against the hooks 2 Lock the adapter by pressing it down 3 To remove the adapter perform the in...

Page 11: ...ts in the switch box The insulation resistance of the compressor is OK There are NO damaged components or squeezed pipes on the inside of the indoor and outdoor units There are NO refrigerant leaks Th...

Page 12: ...CH E H HEATER F U FU FOR CHARACTERISTICS FUSE REFER TO PCB INSIDE YOUR UNIT FG CONNECTOR FRAME GROUND H HARNESS H P LED V L PILOT LAMP LIGHT EMITTING DIODE HAP LIGHT EMITTING DIODE SERVICE MONITOR GRE...

Page 13: ......

Page 14: ......

Page 15: ......

Page 16: ...3P482320 8K 2018 09 Copyright 2018 Daikin...

Reviews: