4. I

NSTALLATION

 

OF

 

LIQUID

 

PIPES

 

AND

 

EQUALIZER

 

PIPES

Cutting the field supplied equalizer pipes

Use the following tables in case dimension A is 300 mm (refer to

"Dimensions for installation" on page 3

If dimension A exceeds 300 mm, extend the L dimension of the
equalizer pipes 1 and 2 accordingly.

For L dimension of equalizer pipes 1 and 2, dimension B of the field
supplied angled joint as in table 12 on page 5 has been taken into
account. If dimension B of the angled joint you use is different from
that dimension B, adjust the L dimension of the equalizer pipes 1 and
2 accordingly.

Table 11 

Table 12

Cutting liquid reducer (1)

Connection piping

Connect the liquid pipes and equalizer pipes as shown in the
figure below.
Before connecting the pipes, first connect the liquid joint and the
liquid reducer (1).

Refer to 

"Dimensions for installation" on page 3

.

Keep the joint in a horizontal position as shown in view A in the
figure below

Connect the liquid reducer (1) in an angle of 40° and bend the
field supplied liquid pipe up to the stop valve as shown in the
figure, see view A in the figure below.

Refer to the installation manual delivered with the outdoor unit
for cautions on brazing pipes.

Refer to 

"Pipe size selection and cutting position of the joint" on

page 3

 for the cutting requirements.

5. A

FTER

 

CONNECTION

 

OF

 

THE

 

PIPING

Connection piping between the outdoor and indoor unit

All piping must be executed according to instructions in the
installation manual of the outdoor unit and an air tight test must be
performed after complete installation of the piping.

Insulation of joints

Step 1:  Fit the insulation (1) around the reducer (2) and keep it in
place with tape (

) (3).

Step 2: Fit the insulation (4) around the joint (5) and keep it in place
with tape (

) (6) without leaving a gap between the two insulated

parts.

Step 3:  Seal the seam between the insulation and the field piping
insulation (

) with tape (

) (7).

Step 4: Cover the insulated parts completely with tape (

) without

leaving any gaps (8).

Equalizer pipe

Joint (angle of 90°)

Pipe 1 (L mm) Pipe 2 (L mm)

B (mm)

95

60

17

1

Connection to liquid pipe (field supply)

2

Connection to liquid joint

3

Cutting position

4

No cutting for 18 Hp

L

B

B

20~32 Hp

1

2

3

4

1

Liquid accessory pipe (1) supplied with the outdoor unit

2

Liquid pipe (1) (field supply) (select the pipe length on site)

3

Equalizer accessory pipe (1) supplied with the outdoor unit

4

Liquid joint 

5

Liquid reducer (1)

6

Joint (angle of 90°) (field supply) refer to table 12 on page 5

7

Equalizer pipe (2) (field supply) refer to table 11 on page 5

8

Equalizer pipe (1) (field supply) refer to table 11 on page 5

9

Liquid pipe (field supply) (select the pipe length on site)

10

Equalizer pipe (field supply) (select the pipe length on site)

11

Liquid accessory pipe (2) supplied with the outdoor unit

All required tape is field supply.

In case of indoor installation, make sure that the tape
is of the fireproof type in order to comply with local
regulations.

8

3

6

11

7

40

°

10

4

9

8

10

5

4

6

7

2

1

3

0

°±

15

A

A

view

1

2

3

5

6

7

8

4

3

2

1

4

3

Summary of Contents for BHFQ23P1357

Page 1: ...INSTALLATION MANUAL BHFQ23P907 BHFQ23P1357 Outdoor unit multi connection piping kit...

Page 2: ...8 6 ID 31 8 ID 25 4 1 ID 31 8 ID 28 6 ID 28 6 ID 25 4 ID 19 1 ID 22 2 ID 25 4 1 ID 22 2 ID 19 1 ID 15 9 ID 19 1 ID 15 9 1 ID 19 1 ID 22 2 ID 25 4 OD 25 4 ID 28 6 1 ID 28 6 ID 31 8 OD 31 8 2 ID 19 1 ID...

Page 3: ...antities and specifications A 1 0 15 view B 1 view 120 mm 500 mm When installing the multi outdoor system connect the units as shown in the figure below If installed in a different order the outdoor u...

Page 4: ...28 6x1 0 1 2H 22 2x1 0 1 2H 15 9x1 0 O 20 22 Hp 28 6x1 0 1 2H 28 6x1 0 1 2H 15 9x1 0 O 24 Hp 34 9x1 21 1 2H 28 6x1 0 1 2H 15 9x1 0 O 26 32 Hp 34 9x1 21 1 2H 28 6x1 0 1 2H 19 1x1 0 1 2H Total capacity...

Page 5: ...it 50 and connect the HP LP gas reducer 2 see view A in the figure below Refer to Pipe size selection and cutting position of the joint on page 3 for the cutting requirements Outdoor unit Pipe 1 L mm...

Page 6: ...n the outdoor and indoor unit All piping must be executed according to instructions in the installation manual of the outdoor unit and an air tight test must be performed after complete installation o...

Page 7: ...6 has been taken into account If dimension B of the angled joint you use is different from that dimension B adjust the L dimension of HP LP gas pipes 1 5 accordingly Table 15 Table 16 1 Liquid joint 3...

Page 8: ...the figure Refer to the installation manual delivered with the outdoor unit for cautions on brazing pipes Refer to Pipe size selection and cutting position of the joint on page 3 for the cutting requi...

Page 9: ...e type without stoppers If dimension B of the angled joint you use is different from that dimension B and or if the joints for same diameter pipes have stopppers adjust the L dimension of suction gas...

Page 10: ...igure below Bend the field supplied liquid pipe up to the stop valve as shown in the figure below Refer to the installation manual delivered with the outdoor unit for cautions on brazing pipes Refer t...

Page 11: ...page 5 6 Liquid reducer 1 7 Liquid pipe 2 field supply select the pipe length on site 8 Equalizer pipe field supply select the pipe length on site 9 Liquid accessory pipe 2 supplied with the outdoor...

Page 12: ...ction gas pipes only For L dimension of suction gas pipes 1 3 dimension B of the field supplied angled joint as in table 25 on page 11 has been taken into account If dimension B of the angled joint yo...

Page 13: ...80 67 262 59 42 44 Hp 80 97 262 59 46 48 Hp 80 97 256 47 Outdoor unit Joint angle of 90 field supply B mm 34 44 Hp 17 46 48 Hp 23 Suction gas reducer 1 Unit A Suction gas reducer 1 Unit B 1 Connectio...

Page 14: ...joint 1 3 Cutting position 4 Connection to liquid joint 2 5 No cutting for 34 Hp 1 Liquid pipe accessory 1 supplied with the outdoor unit 2 Liquid pipe field supply select the pipe length on site 3 Li...

Page 15: ...168 168 244 44 48 212 195 160 168 168 232 Outdoor unit Joint angle of 90 field supply Joint 1 B mm Joint 2 B mm Joint 3 B mm 34 Hp 29 23 23 36 38 Hp 29 29 23 40 Hp 29 29 29 42 Hp 29 29 23 44 48 Hp 29...

Page 16: ...oint 5 angle of 90 field supply refer to table 33 on page 14 22 Suction gas pipe 2 field supply refer to table 30 on page 14 23 HP LP gas pipe 2 field supply refer to table 32 on page 14 24 Suction ga...

Page 17: ...and 3 and HP LP gas reducer 2 and 3 Be sure to foresee enough space for brazing and piping work under the unit 1 Liquid pipe 3 Suction gas pipe 2 HP LP gas pipe 4 Equalizer pipe Suction gas accessory...

Page 18: ...HP LP gas accessory pipe 1 supplied with the outdoor unit 8 HP LP gas reducer 1 9 Suction gas reducer 2 10 HP LP gas pipe field supply select the pipe length on site 11 HP LP gas reducer 3 12 HP LP ga...

Page 19: ...NOTES NOTES...

Page 20: ...Zandvoordestraat 300 B 8400 Oostende Belgium Copyright Daikin 4PW38477 1...

Reviews: