9 Commissioning
Installation manual
40
EBLA04~E23V3 + EDLA04~E23V3
Daikin Altherma 3 M
4P685229-1A – 2022.05
9
Commissioning
NOTICE
General
commissioning
checklist.
Next
to
the
commissioning instructions in this chapter, a general
commissioning checklist is also available on the Daikin
Business Portal (authentication required).
The general commissioning checklist is complementary to
the instructions in this chapter and can be used as a
guideline and reporting template during commissioning and
hand-over to the user.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.
NOTICE
The unit contains an automatic air purge valve. Make sure
it is open. All automatic air purge valves in the system (in
the unit, and in the field piping – if any) must remain open
after commissioning.
INFORMATION
Protective functions – "Installer-on-site mode"
. The
software is equipped with protective functions, such as
room antifrost. The unit automatically runs these functions
when necessary.
During installation or service this behaviour is undesired.
Therefore, the protective functions can be disabled:
▪
At first power-on:
The protective functions are
disabled by default. After 12 hours they will be
automatically enabled.
▪
Afterwards:
An installer can manually disable the
protective functions by setting [9.G]:
Disable
protections
=
Yes
. After his work is done, he can
enable the protective functions by setting [9.G]:
Disable protections
=
No
.
9.1
Checklist before commissioning
1
After the installation of the unit, check the items listed below.
2
Close the unit.
3
Power up the unit.
You read the complete installation instructions, as
described in the
installer reference guide
.
The
outdoor unit
is properly mounted.
The switchbox is rotated back and correctly engaged in
the switchbox holder.
Field wiring
Be sure that the field wiring has been carried out
according to the instructions described in the chapter
15], according to the wiring
diagrams and according to the applicable legislation.
The system is properly
earthed
and the earth terminals
are tightened.
The
fuses
or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The
power supply voltage
matches the voltage on the
identification label of the unit.
There are NO
loose connections
or damaged electrical
components in the switch box.
There are NO
damaged components
or
squeezed
pipes
on the inside of the outdoor unit.
Only for models with integrated backup heater (F1B: field
supply), or if the external backup heater kit (F1B: factory-
mounted in the backup heater kit) is installed:
Backup heater circuit breaker
F1B is turned ON.
Only for tanks with built-in booster heater:
Booster heater circuit breaker
F2B (field supply) is
turned ON.
The correct pipe size is installed and the
pipes
are
properly insulated.
There are no
water leaks
inside the outdoor unit.
The
shut-off valves
are properly installed and fully open.
The
automatic air purge valve
is open.
The
pressure relief valve
purges water when opened.
Clean water MUST come out.
The
minimum water volume
is guaranteed in all
conditions. See "To check the water volume and flow rate"
in
12].
(if applicable) The
domestic hot water tank
is filled
completely.
The
automatic air purge valve
is open.
9.2
Checklist during commissioning
The
minimum flow rate
is guaranteed in all conditions.
See "To check the water volume and flow rate" in
12].
To perform an
air purge
.
To perform a
test run
.
To perform an
actuator test run
.
Underfloor screed dryout function
The underfloor screed dryout function is started (if
necessary).
9.2.1
To check the minimum flow rate
1
Check the hydraulic configuration to find out which
space heating loops can be closed by mechanical,
electronic, or other valves.
—
2
Close all space heating loops that can be closed.
—
3
41]).
—
4
Read out the flow rate
(a)
and modify the bypass valve
setting to reach the minimum required flow rate + 2 l/
min.
—
(a)
During pump test run, the unit can operate below the minimum
required flow rate.
If operation is…
Then the minimum required
flow rate is…
Cooling
10 l/min
Heating
6 l/min