Drain piping work

Installation of drain piping

Install  the  drain  piping  as  shown  in  the  figure  and  take  measures
against  condensation.  Improperly  rigged  piping  could  lead  to  leaks
and eventually wet furniture and belongings.

Install the drain pipes.
- Keep piping as short as possible and slope it downwards at a 

gradient of at least 1/100 so that air may not remain trapped 
inside the pipe.

- Keep pipe size equal to or greater than that of the connecting 

pipe (vinyl pipe of 20 mm nominal diameter and 26 mm outer 
diameter).

- Push the supplied drain hose as far as possible over the 

drain socket.

- Tighten the metal clamp until the screw head is less than 

4 mm from the metal clamp part as indicated in the 
illustration.

- Wrap the supplied large sealing pad over the metal clamp 

and drain hose to insulate and fix it with clamps.

- Insulate the complete drain piping inside the building (field 

supply).

- If the drain hose cannot be sufficiently set on a slope, fit the 

hose with drain raising piping (field supply).

After piping work is finished, check drainage flows 
smoothly.

• Gradually insert approximately 1L of water into the drain pan

to check drainage in the manner described below.

• Gradually pour approximately 1L of water from the outlet

hole into the drain pan to check drainage.

• Check the drainage.

When electric wiring work is finished

Check  drainage  flow  during  COOL  running,  explained  in 

"Test

operation" on page 8

.

When electric wiring work is not finished

Remove  the  switch  box  cover  and  connect  the  single-phase
power supply and the remote controller to the terminals. (Refer
to  chapter 

"Electric  wiring  work"  on  page 6

  for  switch  box

attachment/detachment) (Refer to 

figure 9

 and 

10

)

Connect the single-phase power supply to connections 1 and 2
(as shown in the figure) on the power supply terminal board and
confirm drain operation.

Be aware that the fan will turn during the operation.

1

Drain socket (attached to the unit)

2

Drain hose (supplied with the unit)

1

Drain socket (attached to the unit)

2

Drain hose (supplied with the unit)

3

Metal clamp (supplied with the unit)

4

Large sealing pad (supplied with the unit)

5

Drain piping (field supply)

Connect the drain pipe after 
removing the rubber cap and 
insulation tubing attached to 
the connection hole.

Drain pipe connection hole

Refrigerant pipes

2

1

5

2

3

4

4 mm

3
4

2

A

A'

A-A'

1

1

Drain outlet

Air outlet

Bucket

Refrigerant pipes

Portable pump

L N

L N

1 2

3

4PEN461568-1.book  Page 5  Thursday, October 20, 2016  11:50 AM

Summary of Contents for ADEQ-C

Page 1: ...INSTALLATION MANUAL ADEQ35C2VEB ADEQ50C2VEB ADEQ60C2VEB ADEQ71C2VEB ADEQ100C2VEB ADEQ125C2VEB Split System air conditioners 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 2: ... 2 2 3 680 1 3 4 2 680 200 45 1 5 6 3 4 2 680 1 5 3 4 2 7 800 630 A B 2 1 4 3 4 1 1 2 1 3 5 2 125 460 160 160 300 375 1 3 2 460 7a 7b 4 4 A A 125 5 4 7 6 3 300 1 2 3 4 5 6a 6b 6c 7a 7b 7c 8 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 3: ...il Certificato C 07 Σημείωση όπως καθορίζεται στο A και κρίνεται θετικά από το B σύμφωνα με το Πιστοποιητικό C 08 Nota tal como estabelecido em A e com o parecer positivo de B de acordo com o Certificado C 09 Примечание как указано в A и в соответствии с положительным решением B согласно Свидетельству C 10 Bemærk som anført i A og positivt vurderet af B i henhold til Certifikat C 11 Information en...

Page 4: ... 5 m from the floor Where the air contains high levels of salt such as air near the ocean and where voltage fluctuates a lot e g in factories Also in vehicles or vessels Do not install accessories on the casing directly Drilling holes in the casing may damage electrical wires and consequently cause fire Sound pressure level is less than 70dB A Accessories Check if the following accessories are inc...

Page 5: ...h relevant European and national regulations 3 Use suspension bolts for installation Check whether the ceiling is strong enough to support the weight of the indoor unit If there is a risk reinforce the ceiling before installing the unit Preparations before installation 1 Relation of ceiling opening to unit and suspension bolt position See figure 5 For installation choose one of the possibilities a...

Page 6: ... side flange field supply Connect the flange to the main unit with accessory screws 7 Wrap the intake side flange and duct connection area with aluminum tape or something similar to prevent air escaping Air outlet side Connect the duct according to the air inside of the outlet side flange Wrap the outlet side flange and the duct connection area with aluminum tape or something similar to prevent ai...

Page 7: ...to the piping will create large quantities of oxidized film on the inside of the pipes adversely affecting valves and compressors in the refrigerating system and preventing normal operation When brazing while inserting nitrogen into the piping nitrogen must be set to 0 02 MPa with a pressure reducing valve just enough so that it can be felt on the skin Be sure to insulate the duct to prevent conde...

Page 8: ... check drainage in the manner described below Gradually pour approximately 1L of water from the outlet hole into the drain pan to check drainage Check the drainage When electric wiring work is finished Check drainage flow during COOL running explained in Test operation on page 8 When electric wiring work is not finished Remove the switch box cover and connect the single phase power supply and the ...

Page 9: ...e units When none are available follow the instructions below Do not connect wires of different gauge to the same power supply terminal Looseness in the connection may cause overheating When connecting wires of the same gauge connect them according to the figure Use the specified electric wire Connect the wire securely to the terminal Lock the wire down without applying excessive force to the term...

Page 10: ...he airflow automatic adjustment function Airflow automatic adjustment is the volume of blow off air that has been automatically adjusted to the rated quantity 1 Make sure the test run is done with a dry coil If the coil is not dry run the unit for 2 hours with fan only to dry the coil 2 Check if the power supply wiring to the air conditioning unit is completed along with the duct installation If a...

Page 11: ...eration accordingly to protect the unit 1 Open the gas side stop valve 2 Open the liquid side stop valve 3 Electrify crank case heater for 6 hours 4 Set to cooling operation with the remote controller and start operation by pushing ON OFF button 5 Press Inspection Test Operation button 4 times and operate at Test Operation mode for 3 minutes 6 Press Inspection Test Operation button and operate nor...

Page 12: ...CN E HA HE HL HN HR MR _A MR _B S U V W X A CONNECTION CONNECTOR Q L OVERLOADPROTECTOR D V D DIODE Q M THERMOSWITCH DB DIODEBRIDGE R RESISTOR DS DIPSWITCH R T THERMISTOR E H HEATER RC RECEIVER F U FU FORCHARACTERISTICS REFERTOPCBINSIDEYOURUNIT FUSE S C LIMITSWITCH FG CONNECTOR FRAMEGROUND S L FLOATSWITCH H HARNESS S NPH PRESSURESENSOR HIGH H P LED V L PILOTLAMP LIGHTEMITTINGDIODE S NPL PRESSURESEN...

Page 13: ...4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 14: ...4PEN461568 1 book Page 2 Thursday October 20 2016 11 50 AM ...

Page 15: ...3 1 2 3 4 5 P1 P2 P1 P2 P1 P2 6 6 1 2 L N 3 2 3 2 3 1 2 3 4 5 P1 P2 P1 P2 6 L N L N 1 1 1 1 1 1 L N 1 2 3 L N 1 2 3 1 2 3 L N 1 2 3 1 2 3 L N 1 2 3 16 1 4 2 3 5 7 8 11 12 6 9 6 L N 1 2 3 P1 P2 F1 F2 T1 T2 Sec A A 15 14 A A A A 10 13 6 6 9 10 11 12 13 14 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 16: ...4P461568 1 2016 09 Copyright 2016 Daikin 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Reviews: