background image

 

6

Electric wiring work

General instructions

All field wiring and components must be installed by a licensed
electrician and must comply with relevant European and national
regulations.

Use copper wire only.

Follow the "Wiring diagram" attached to the unit body to wire the
outdoor unit, indoor units and the remote controller. For details
on  hooking  up  the  remote  controller,  refer  to  the  "Installation
manual of the remote controller".

All wiring must be performed by an authorized electrician.

If  the  supply  cord  is  damaged,  it  must  be  replaced  by  the
manufacturer,  a  service  agent  or  similarly  qualified  persons  in
order to avoid a hazard.

Attach the  earth leakage circuit  breaker  and  fuse to  the power
supply line.

A  main  switch  or  other  means  for  disconnection,  having  a
contact separation in all poles, must be incorporated in the fixed
wiring in accordance with relevant local and national legislation.
Note  that  the  operation  will  restart  automatically  if  the  main
power supply is turned off and then turned back on again.

Refer  to  the  installation manual  delivered with  the  outdoor  unit
for  the  size  of  power  supply  electric  wire  connected  to  the
outdoor unit, the capacity of the earth leakage breaker and fuse
and for wiring instructions.

Be sure to ground the air conditioner.

Do not connect the ground wire to:
- gas pipes: might cause explosions or fire if gas leaks.
- telephone ground wires or lightning rods: might cause 

abnormally high electric potential in the ground during 
lightning storms.

- plumbing pipes: no grounding effect if hard vinyl piping is 

used.

Make sure that earth wire between the pull relief
and terminal is longer than other wires.

Be  sure  that  the  shape  of  the  power  supply
cable and any other cable, before entering unit,
should be as shown in this figure.

All  cables  entering  the  unit  should  be  fixed  by
tie wraps (accessory).

Use  long  sealing  (accesory)  to  block  entrance
of switch box as shown in 

figure 9

.

Electrical characteristics

Specifications for field wire

Wiring example and how to set the remote 
controller

How to connect wiring

Remove the switch box cover as shown in 

figure 10

, and make the

connections.

Precautions

1.

Observe  the  notes  mentioned  below  when  wiring  to  the  power
supply terminal board.
• Use  a  round  crimp-style  terminal  for  insulation  sleeve  for

connection  to  the  terminal  block  for  wiring  the  units.  When
none are available, follow the instructions below.

• Do not  connect  wires  of different gauge to the  same  power

supply  terminal.  (Looseness  in  the  connection  may  cause
overheating.)

• When  connecting  wires  of  the  same  gauge,  connect  them

according to the figure.

Use  the  specified  electric  wire.  Connect  the  wire  securely  to  the
terminal. Lock the wire down without applying excessive force to the
terminal. Use torques according to the table below.

• When  attaching  the  control  box  lid,  make  sure  not  to  pinch

any wires.

• After  all  wiring  connections  are  done,  fill  in  any  gaps  in  the

casing  wiring  holes  with  putty  or  insulation  material  (field
supply) thus to prevent small animals or dirt from entering the
unit from outside and causing short circuits in the control box.

2.

Do not connect wires of different gauge to the same grounding
terminal.  Looseness  in  the  connection  may  deteriorate  the
protection.

3.

Remote controller cords and wires connecting the units should
be located at least 50 mm away from power supply wiring. Not
following  this  guideline  may  result  in  malfunction  due  to
electrical noise.

4.

For the remote controller wiring, refer to the "Installation manual
of the remote controller" supplied with the remote controller.

5.

Never connect the power supply wiring to the terminal board for
transmission  wiring.  This  mistake  could  damage  the  entire
system.

NOTE

For  details,  refer  to  "Electrical  data"  in  the  technical
data book.

Wire

Size (mm

2

)

Length

Between 

indoor units

H05VV-U4G

(a),(b)

(a) Shows only in case of protected pipes. Use H07RN-F in case of no protection.
(b) Run transmission wiring between the indoor and outdoor units through a conduit 

to protect against external forces, and feed the conduit through the wall together 
with refrigerant piping.

2.5

Unit-Remote 

controller

Sheathed wire 

(2 wire)

(c)

(c) Use double insulation wire for remote controller (sheath thickness: ≥1 mm) or run 

wires through a wall or conduit so that the user cannot come in contact with them.

0.75–1.25

Max. 500 m

(d)

(d) This length shall be the total extended length in the system of the group control.

A

B

A<B

LN

1

Switch box cover

2

Switch box low voltage wiring inlet

3

Switch box high voltage wiring inlet

4

Wiring diagram

5

Switch box

Tightening torque (N•m)

Terminal block for remote controller

0.79~0.97

Terminal block for power supply

1.18~1.44

NOTE

The  customer  has  the  ability  to  select  the  remote
controller thermistor.

1

2

3

1

Round crimp-style terminal

2

Attach insulation sleeve

3

Wiring

4PEN461568-1.book  Page 6  Thursday, October 20, 2016  11:50 AM

Summary of Contents for ADEQ-C

Page 1: ...INSTALLATION MANUAL ADEQ35C2VEB ADEQ50C2VEB ADEQ60C2VEB ADEQ71C2VEB ADEQ100C2VEB ADEQ125C2VEB Split System air conditioners 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 2: ... 2 2 3 680 1 3 4 2 680 200 45 1 5 6 3 4 2 680 1 5 3 4 2 7 800 630 A B 2 1 4 3 4 1 1 2 1 3 5 2 125 460 160 160 300 375 1 3 2 460 7a 7b 4 4 A A 125 5 4 7 6 3 300 1 2 3 4 5 6a 6b 6c 7a 7b 7c 8 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 3: ...il Certificato C 07 Σημείωση όπως καθορίζεται στο A και κρίνεται θετικά από το B σύμφωνα με το Πιστοποιητικό C 08 Nota tal como estabelecido em A e com o parecer positivo de B de acordo com o Certificado C 09 Примечание как указано в A и в соответствии с положительным решением B согласно Свидетельству C 10 Bemærk som anført i A og positivt vurderet af B i henhold til Certifikat C 11 Information en...

Page 4: ... 5 m from the floor Where the air contains high levels of salt such as air near the ocean and where voltage fluctuates a lot e g in factories Also in vehicles or vessels Do not install accessories on the casing directly Drilling holes in the casing may damage electrical wires and consequently cause fire Sound pressure level is less than 70dB A Accessories Check if the following accessories are inc...

Page 5: ...h relevant European and national regulations 3 Use suspension bolts for installation Check whether the ceiling is strong enough to support the weight of the indoor unit If there is a risk reinforce the ceiling before installing the unit Preparations before installation 1 Relation of ceiling opening to unit and suspension bolt position See figure 5 For installation choose one of the possibilities a...

Page 6: ... side flange field supply Connect the flange to the main unit with accessory screws 7 Wrap the intake side flange and duct connection area with aluminum tape or something similar to prevent air escaping Air outlet side Connect the duct according to the air inside of the outlet side flange Wrap the outlet side flange and the duct connection area with aluminum tape or something similar to prevent ai...

Page 7: ...to the piping will create large quantities of oxidized film on the inside of the pipes adversely affecting valves and compressors in the refrigerating system and preventing normal operation When brazing while inserting nitrogen into the piping nitrogen must be set to 0 02 MPa with a pressure reducing valve just enough so that it can be felt on the skin Be sure to insulate the duct to prevent conde...

Page 8: ... check drainage in the manner described below Gradually pour approximately 1L of water from the outlet hole into the drain pan to check drainage Check the drainage When electric wiring work is finished Check drainage flow during COOL running explained in Test operation on page 8 When electric wiring work is not finished Remove the switch box cover and connect the single phase power supply and the ...

Page 9: ...e units When none are available follow the instructions below Do not connect wires of different gauge to the same power supply terminal Looseness in the connection may cause overheating When connecting wires of the same gauge connect them according to the figure Use the specified electric wire Connect the wire securely to the terminal Lock the wire down without applying excessive force to the term...

Page 10: ...he airflow automatic adjustment function Airflow automatic adjustment is the volume of blow off air that has been automatically adjusted to the rated quantity 1 Make sure the test run is done with a dry coil If the coil is not dry run the unit for 2 hours with fan only to dry the coil 2 Check if the power supply wiring to the air conditioning unit is completed along with the duct installation If a...

Page 11: ...eration accordingly to protect the unit 1 Open the gas side stop valve 2 Open the liquid side stop valve 3 Electrify crank case heater for 6 hours 4 Set to cooling operation with the remote controller and start operation by pushing ON OFF button 5 Press Inspection Test Operation button 4 times and operate at Test Operation mode for 3 minutes 6 Press Inspection Test Operation button and operate nor...

Page 12: ...CN E HA HE HL HN HR MR _A MR _B S U V W X A CONNECTION CONNECTOR Q L OVERLOADPROTECTOR D V D DIODE Q M THERMOSWITCH DB DIODEBRIDGE R RESISTOR DS DIPSWITCH R T THERMISTOR E H HEATER RC RECEIVER F U FU FORCHARACTERISTICS REFERTOPCBINSIDEYOURUNIT FUSE S C LIMITSWITCH FG CONNECTOR FRAMEGROUND S L FLOATSWITCH H HARNESS S NPH PRESSURESENSOR HIGH H P LED V L PILOTLAMP LIGHTEMITTINGDIODE S NPL PRESSURESEN...

Page 13: ...4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 14: ...4PEN461568 1 book Page 2 Thursday October 20 2016 11 50 AM ...

Page 15: ...3 1 2 3 4 5 P1 P2 P1 P2 P1 P2 6 6 1 2 L N 3 2 3 2 3 1 2 3 4 5 P1 P2 P1 P2 6 L N L N 1 1 1 1 1 1 L N 1 2 3 L N 1 2 3 1 2 3 L N 1 2 3 1 2 3 L N 1 2 3 16 1 4 2 3 5 7 8 11 12 6 9 6 L N 1 2 3 P1 P2 F1 F2 T1 T2 Sec A A 15 14 A A A A 10 13 6 6 9 10 11 12 13 14 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Page 16: ...4P461568 1 2016 09 Copyright 2016 Daikin 4PEN461568 1 book Page 1 Thursday October 20 2016 11 50 AM ...

Reviews: