2)
Pour the formulation into the formulation tank and flushing solution into the flush tank. Use
Dyna-Fog flushing solution in the flush tank. Tighten both caps securely.
3)
Open the fiberglass pump enclosure and place the Master Power Switch in the "OFF" position.
4)
At the remote box place the Blower/Atomizer switch to the "ON" position.
5)
While observing the Tachometer in the fiberglass enclosure, place the master switch to the
"ON" position. The atomizer speed should be between 28,000 and 30,000 RPM. If the speed
is not in this range, shutoff the switch immediately and check the sprayers battery voltage.
The voltage should be between 12.8 and 13.8 Volts DC. If the voltage is in this range and the
speed is lower than 28,000 rpm, contact a Curtis Dyna-Fog, Ltd. representative. NOTE: If the
voltage is too low, make sure the battery is properly charged and that all electrical connections
on the machine and the vehicle are correct.
6)
Close the fiberglass pump enclosure and make sure it is latched properly. The pump
enclosure and the stainless steel pump cover are designed so that they can be locked using a
pad lock. To prevent tampering with the machine while it is left unattended, you can
completely "Lock Down" the machine by placing the Master Switch in the "OFF" position and
locking the fiberglass pump enclosure and stainless steel pump cover.
7)
From the Remote Box, actuate the Atomizer Direction Switch to elevate the atomizer to the
correct angle. The machine is pre-set so that the atomizer will be at a 45
o
upward angle when
the actuator is fully extended and at 0
0
(horizontal)
when fully retracted. Adjust the angle to
your formulation manufacturer's label recommendation. Typically, a 45
0
angle is used when
doing outdoor spraying. For custom applications, you can change the maximum and minimum
angle stop points by moving the actuator to the lower hole location in the actuator clevis as
shown below. The atomizer can also be rotated horizontally by manually loosening the clamp
knob and positioning the atomizer in the desired direction.
8)
At the remote box, place the Spray ON/OFF Switch to the "OFF" position and the
Formulation/Flush Switch to the Formulation position.
9)
Once you have reached the area you are intending to spray, place the Atomizer/Blower switch
to the "ON" position. As a safety feature, the pump will not operate until the Atomizer/Blower
Switch is in the "ON" position.
10)
After the atomizer is fully up to operating speed (3-5 seconds), and once your vehicle reaches
your application driving speed, spray can be started and stopped using the Spray ON/OFF
Switch.
11)
To stop spraying, first turn OFF the spray. Wait at least one minute to purge liquid from the
atomizer sleeve before turning OFF the Atomizer/Blower switch.
16
Summary of Contents for DYNA-FOG DYNA-JET L30 2 Series
Page 21: ... ...
Page 22: ...Terminal Strip Wire Connection Diagram 22 ...
Page 24: ......
Page 26: ... ...
Page 28: ...28 ...
Page 30: ...Pump Bracket Assembly L30 30 ...
Page 38: ......
Page 41: ...Pump Enclosure Wiring Diagram L30 41 ...
Page 42: ...Remote Control Box Schematic L30 Series 2 42 ...