30
Lotem 400/ Lotem 400 Quantum Site Preparation Guide
13.
Is UPS required?
If yes, has the UPS been ordered?
14.
Is a 20 A service (16 A in Europe) with a slow-blow fuse or breaker installed,
and a dedicated ground for the device?
15.
Is the AC service for the workstation installed and originating from the same
supply panel as the device AC service?
16.
Does the air supply flow (tested using air supply gauge 92-0373A) meet
specifications? (See the
Air Supply Qualification Procedure
Record the test results in the following table.
Yes
No
Yes
No
Yes
No
Comments:
Yes
No
Comments:
Yes
No