Ridgefield
19803-100 Rev g (10-17)
© Copyright 2011, Creative Playthings
Page 19
ASSeMbly inSTRuCTionS
Step 25 — Assemble Ridge Cap:
Align Ridge Cap Part A (X) overlapping Ridge Cap Part B
(Y) as shown at right. ensure that the ends of the Ridge
Cap parts align before fastening using #8 x 2" screws. each
screw should pass through Ridge Cap Part A and into Ridge
Cap Part B. leave the screw head flush to the surface of
Ridge Cap Part A.
Step 26 — Mount Ridge Cap:
Before putting the Ridge Cap in place, drill a series of 1/8" di-
ameter pilot holes through the top board of each roof panel.
The pilot holes should be at least 3" from the end of the roof
board and approximately 3/4" from the top edge. Space the
pilot holes every 10 to 12 inches.
Put the Ridge Cap in place at the peak of the roof, as shown.
The ends of the Ridge Cap should be flush with the ends of
the roof.
from inside the gym, fasten the Ridge Cap using #8 x 1-1/4"
screws, through the pilot holes and into the Ridge Cap.
Step 27 — dormer & gable fans:
Assemble and install the dormer as directed by the instruc-
tions included in the dormer package.
install the gable fans as directed by the instructions includ-
ed in the gable fan package.
Ridge Cap Part B (Y)
Ridge Cap Part A (X)
AY
AX