Step 19

: Secure the remaining 2 8x12/ 20mm bolts and 8mm washers into the 

touchscreen’s lower VESA mounting holes through the lower part 000.  

 

 

Step 20

: Tighten the 4 8x20mm CHB’s on the lower part 000 

 

 

Step 21

: The actuators need to be initialized to function correctly.  

 

Using the buttons shown above lower the touchscreen until it hits its lowest vertical 

limit (indicated by a 1 on the LED screen on the control panel). Continue to hold the 

button down until the actuators move up slightly.  

 

Press the rotating arrow button and lower the touchscreen to the horizontal 

position (indicated by a 2 on the LED control panel). Continue to hold the button 

down until the actuators move up slightly.  

 

Once both steps are completed the trolley is ready to go. 

 

 
 
 

Additional Notes 

 

 

 

Transportation: When moving your tilt trolley around your campus, place the 

touchscreen in the vertical position and lower  the touchscreen to within 10-

20mm of the castor legs (parts 001).  Ensure all leads are stowed safely and 

out of the way of moving parts. 

 

 

Safe Operation of the trolley: The Lift actuators have a built in safety feature 

(Pizo) where any change in pressure between sides will automatically stop 

and reverse the movement of the unit. This will also happen if the panel is 

lowered onto the castor legs. 

 

 

Error E01: The E01 error will appear if the actuators get themselves out of 

sync. If you get the E01 error follow the initialising procredure in step 20. 
 

For any other errors please contact CommBox support on 02 9975 6001, or 

alternatively you can log it through the website 

here

Summary of Contents for Tilt Trolley

Page 1: ......

Page 2: ...you have received a paper copy of the instruction guide please contact CommBox Support for an electronic copy of the guide This will enable you to expand out the photos for better recognition of Parts...

Page 3: ...ng of this product ease of construction was our highest priority One of the steps taken was to use Cup Head Bolts referred to as CHB The use of this fastening system enables construction with limited...

Page 4: ...arts 020 to parts 001 Once castors are secured using a soft blow hammer knock in the plastic end caps 008 into the ends of 001 Note the lockable castors go to the rear shorter end Step 2 Align parts 0...

Page 5: ...ecure parts 004 to 005 Step 4 Minimum of two people required for this step Aligning the control cable of 013 to the inside secure both columns to the base structure using 8x 6x25mm bolts 4off 8x20mm C...

Page 6: ...There is a second mounting hole for the 8x20mm CHB from the side higher than shown here The second 8x20mm CHB that secures the cable tray assembly is shown below NOTE The 8x20mm CHB circled will need...

Page 7: ...all bolts are in secure the 8x20mm CHB s from Step 6 do not over tighten the 10mm nut Step 8 Using parts 002 018 one 10x 30mm CHB bolt 10mm nylock nut per side place two 018 washers between parts 002...

Page 8: ...Step 9 Place the cable tray structure 006 onto the lift columns 013 The fixing screws should be lined up as shown in the upper mounting position...

Page 9: ...re pushed through the large hole in parts 006 Step 9 Using 8 6x25mm bolts secure parts 006 to 013 lift Columns as shown above Step 10 Using 4x12mm bolts and 4mm nylock nuts secure the control box part...

Page 10: ...13 actuators column plug into 1 2 on the control box Actuators 011 tilting plug into 3 4 NOTE Please cable tie any leads after observing how much slack is required during the operation of the trolley...

Page 11: ...sition The cradle should be level with the vertical actuators Step 16 Temporarily plug the Control Head into the powerboard Once it has been plugged in and all personnel tools cabling etc have been se...

Page 12: ...panels supplied hardware or two of the 8x12 20mm bolts and 8mm washers Apply the foot brackets for the remainder of the assembly Step 17 Using a minimum of two people raise the panel and locate part 0...

Page 13: ...slightly Once both steps are completed the trolley is ready to go Additional Notes Transportation When moving your tilt trolley around your campus place the touchscreen in the vertical position and lo...

Reviews: