5/47
5.
TRANSPORTATION AND INSTALLATION
During transportation, take necessary precautions against the risk of falling down and being turned upside down for the
product.
Place the product onto a flat and solid ground.
Do not install the product near the flammable and explosive materials and do not keep any flammable and explosive
material near the furnace, while it is working.
Keep surely a fire extinguisher near the furnace and check whether the periodical checking of the fire extinguisher has
been implemented or not.
6. GENERAL PRINCIPLES
The users agree and accept to be in conformity with all requirements included in using manual, otherwise the machine shall be deemed
OUT OF GUARANTEE COVERAGE.
The user also accepts that he/she was fully informed about the limited guarantee liability.
Any living body or any object should not be placed on machines. In addition, any living body should not be put inside the machines.
It should not be allowed the children or any other unauthorized persons to operate the machines.
Any electrical operating machines should be cleaned after the required electrical connections switched off.
The electrical products should never be operated if any sufficient grounding installation had not been practiced in addition; the LEAK
CURRENT RELAY and fuse groups had not been installed in control box supplying the electrical energy to the machine.
-Table 2-
The cover of any machine should not be opened during the period of working.
Be careful not to squeeze your hands while closing the covers.
The machines and covers should not be treated as step or ladder in any case.
The electrical devices should never be washed in the manner of spraying water. They should be cleaned by means of rubbing after
switching the power off the power had been switched off.
Any scratchier or stripper tools should not be used during the cleaning.
This manual verifies all machines were tested and the required security controls were done in due diligence so delivered under
operating conditions.
Use rubber gloves during the cleaning and maintenance practices procedures
Do not remove the labels and panels of the devices.
In order to ensure efficient operation of the machines including electrical water heating process and to minimize the energy costs, you
should provide the machine with 50 °C water. In addition, softened water under 15 °Fr hardness should also be used to expand the life
of your machines. If you do not have such required softened water then you should use a separate water softener device.
The manufacturer shall not be responsible for any possible printing mistakes included in both manual and machine introduction leaflet.
MODEL
relay
7478,0555
2x10 A – 30 mA
7478,0125
2x10 A – 30 mA
Summary of Contents for Bain-Mari 7478.0125
Page 1: ...1 47 7478 0555 7478 0125 7478 0455 BAINMARIE INSTRUCTION MANUAL...
Page 4: ...4 47...
Page 9: ...9 47...
Page 14: ...14 47...
Page 20: ...20 47 7478 0555 7478 0125 7478 0455 BENMAR E INSTRUCTION MANUAL...
Page 23: ...23 47...
Page 29: ...29 47 7478 0555 7478 0125 7478 0455 ELEKTRISCHES WASSERBAD BEDIENUNGS UND WARTUNGSANLEITUNG...
Page 37: ...37 47 7478 0555 7478 0125 7478 0455 BAIN MARIE ELECTRIQUE MANUEL D UTILISATION ET D ENTRETIEN...
Page 40: ...40 47...
Page 45: ...45 47 11 SCH MAS LECTRIQUES...
Page 47: ...47 47...