5.1. Maintenance intervals
5 hours after first
putting into operation:
Check drying agent in the drying cells, if necessary fil upl
Daily:
Check warning signs on equipment for good
legibility and completeness
Clean return air filter and housing
(depending on amount of dust collected)
Lamp test: if you press the ”+/-”-button longer than
2 seconds all LED’s must light up
Weekly:
Check function of the main switch
Clean filter of the electrical cabinet
(depending on amount of dust collected)
Monthly:
Check V-belt tension of blower
Every three months:
Clean filter of the regeneration blower
(depending on amount of dust collected)
Every six months:
Exchange return air filter
(depending on amount of dust collected)
Exchange filter of the electrical cabinet
(depending on amount of dust collected)
Check all electrical and mechanical connections for tight fit.
Yearly:
Exchange filter of the regeneration blower
(depending on amount of dust collected
&
This maintenance schedule is calculated for 3-shift operation.
F
The given maintenance intervals are average values.
Check whether in your individual case the maintenance intervals must be
shortened.
64.10-0233GB05
11/02
CTT 1600
Maintenance 5-3