20
6 - START-UP
START-UP SEQUENCE
√
Start-up sequence - Unit ON power supply
Compressor carter resistances operating at least since 8 hours
Off-load voltage measure
Phase sequence check
Pump manual start-up and flow check
Unit ON
Load voltage measure and absorptions
Liquid light check (no bubbles)
Measure of return and supply water temperature
Super-heating and sub-cooling measure
Check no anomalous vibrations are present
Set-point personalization
Climatic curve personalization
Complete and available unit documentation
Operations to perform to start-up the unit.
For details refer to the different manual sections.
Summary of Contents for WSH 100D
Page 9: ...9 4 WATER CONNECTIONS...
Page 12: ...12 WATER CONNECTIONS...
Page 14: ...14 5 ELECTRICAL CONNECTIONS 5 6 CONNECTIONS PERFORMER BY CUSTOMER...
Page 15: ...15 5 ELECTRICAL CONNECTIONS...
Page 16: ...16 5 ELECTRICAL CONNECTIONS...
Page 31: ...31 8 MAINTENANCE...
Page 46: ...46 NOTE...
Page 47: ...47...