background image

 

 1 / 13 

 

 

 

Clenergy China    

 

 

 

 

 

Tel86 592 311 0088 

999-1009 Min'an Rd, Huoju Hi-tech Ind. Dev. Zone 

 

 

Fac86 592 599 5028 

Xiang'an District 361101, Xiamen, Fujian, China 

 

 

[email protected] 

 

1. Introduction 

The  Clenergy  PV-ezRack  SolarFloating  System  is  a  surface  floating 

platform suitable for large-scale civil and commercial installations. The

 

Floater 

is  made  of  high-density  polyethylene  (HDPE).  This  material  is  insoluble  in 

organic  solvents  and  resistant  to  corrosion  by  acids,  alkalis  and  salts.  The 

system  has  the  advantages  of  simple  and  convenient  installation,  stable 

structure and long service life.

 

Please review this manual thoroughly before installing SolarFloating. This 

manual  provides  the  following  contents:  (1)  Installation  planning;  (2) 

Installation instructions; 

Please install SolarFloating System according to this installation guide. It 

meets the GB50009-2012

ASCE7-10 ISO 14713 standards. When installing 

please comply with the appropriate local safety regulations, and pay attention 

to  other  relevant  regulations  in  your  local  region.  The  latest  version  of  the 

installation manual is available on our website 

www.clenergy.com.cn

. 

 

The installer shall comply with the following requirements:  

 

  Complying with all building codes  according to any applicable place or 

country that may supersede this manual. 

  Ensuring  that  PV-ezRack  and  other  products  are  appropriate  for  the 

particular installation and the installation environment. 

  Using only PV-ezRack parts and installer-supplied parts as specified by 

Clenergy (substitution of parts may void the warranty and invalidate the 

letter of certification). 

  Recycling: according to local related statutes. 

  Disassembly: reverse installation process. 

  Ensuring that there are no less than two professionals working on panel 

installation at the one time. 

  Ensuring that related electrical equipment is installed by a professional 

electrician. 

 

Construction process safety statement: 

1. Water construction workers must wear life jackets and wear safety helmets. 

2. In case of severe weather such as strong winds, waves and dense fog, no 

water work is allowed. 

Summary of Contents for PV-ezRack SolarFloating I

Page 1: ...na Telephone 86 592 311 0088 999 1009 Min an Rd Huoju Hi tech Ind Dev Zone Facsimile 86 592 599 5028 Xiang an District 361101 Xiamen Fujian China sales clenergy com cn PV ezRack SolarFloating I Instal...

Page 2: ...iate local safety regulations and pay attention to other relevant regulations in your local region The latest version of the installation manual is available on our website www clenergy com cn The ins...

Page 3: ...areness establish the idea of safety first have a strong sense of responsibility and find timely handling and reporting of safety hazards to ensure smooth construction 2 Tools and Components 2 1 Tools...

Page 4: ...ales clenergy com cn 2 2 Components Components ER SFI MF Main Floater ER SFI AF D Aisle Floater Double ER SFI RS Rear Support Leg ER SFI FS Front Support Leg ER SFI CB Connect Bolt ER SFI CN Connect N...

Page 5: ...lead to the deadlock of bolts and nuts Follow the steps below to reduce this risk 3 2 1 Reduce the friction coefficient Ensure that the thread surface is clean no dirt or contaminant Apply lubricant...

Page 6: ...d in engineering drawings As a result major components of the SolarFloating may be provided in sectional sizes and lengths that vary from those shown in this guide The installation operations detailed...

Page 7: ...tion the scaffolding type is adopted and then laying wooden boards or laying the board directly after the shore is flat requires a certain roughness but no sharp protrusion Construction platform size...

Page 8: ...stallation 4 1 1 Place the Main Floater flat on the ground as shown in Figure 1 4 1 2 Insert the Front and Rear Support Leg into the hexagonal mounting hole of the Main Floater as shown in Figure 2 4...

Page 9: ...28 Xiang an District 361101 Xiamen Fujian China sales clenergy com cn Figure4 4 2 Rear Clamp Installation 4 2 1 Lock the Rear Clamp on the support leg and do not lock the bolt and nut temporarily for...

Page 10: ...strict 361101 Xiamen Fujian China sales clenergy com cn Figure 6 4 3 Connect Two Main Floaters 4 3 1 Use one Aisle Floater to connect the two Main Floaters together and lock them with bolts and nuts P...

Page 11: ...n use the electric drill to drill the Self drilling screw ST6 3 25 through the bolts and nuts and connect the two together as shown in Figure 8 Figure 7 Figure 8 4 4 Peripheral Aisle Floater Installat...

Page 12: ...For each bolt and nut connection point use professional tools to lock the bolts and nuts first and then use the electric drill to drill the Self drilling screw ST6 3 25 through the bolts and nuts and...

Page 13: ...aining PV Modules Figure 13 is the installation effect of a 1 2 unit Figure 13 4 6 Connect the Floating System and Anchor System 4 6 1 Push the installed Floating System into the water as shown in Fig...

Page 14: ...u Hi tech Ind Dev Zone Facsimile 86 592 599 5028 Xiang an District 361101 Xiamen Fujian China sales clenergy com cn according to the actual conditions of the project After tightening the anchor rope f...

Reviews: