torque of the M8 bolt
should not be too large,
and it is better to lock
the plastic parts slightly
deformed.
4.5.2 Repeat the above
method to install the
remaining PV Modules.
Figure 13 is the
installation effect of a
1*2 unit.
Figure 13
4.6 Connect the Floating System and Anchor System
4.6.1 Push the installed
Floating System into the
water as shown in
Figure 14. Use a motor
boat to pull it to the
designated location and
adjust the north-south
orientation of the
system.
4.6.2 Fixed the
Floating
System
according to
the
anchoring
scheme, as shown in
Fig. 15. Commonly
used
anchoring
methods are: pile
anchoring and anchor
block anchoring. The
length of the anchor
rope is determined
Figure 14
Figure 15