Installation Guide_PV-ezRack_ezShade_AU_V1.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
14
page
of 25
Installation Instruction
Fig. 11
Recommended Torque:
M8 Bolts: 18~20 N.m
According to engineering drawings, repeat
the above operations to install other T-Rails
as shown in Fig12. Ensure the end faces of
the Rails are aligned, and all Rails are at
same height. Now fasten all the bolts
tightly.
Two Rail Clamps
Four Rail
Clamps in total
Fig. 12
Note: the installation positions of T-Rail as shown in Fig 13.
Fig. 13
Note:
Apply two Rail Clamps for T-Rail on
each side of Rail.
Control the tool speed.