CLEARSPAN
™
STORAGE MASTER
16
PB02522R6N1D Revision date: 03.22.19
13. Tighten the cross-connector and install a Tek screw as
shown to secure the purlin pipe joint and to secure the
purlin to the cross-connector.
14. Move to the other upper pipe joint on the inside rafter,
place a cross-connector over the joint, and repeat
the steps to install the first two sections of the last
overhead purlin.
NOTE:
Position the cross-connector and purlin on the
rafter pipe joint. Do not remove the temporary bracing
until additional rafters are in place.
To this point, the assembled frame includes two rafters
and three top purlins as shown.
FRAME ASSEMBLY (CONTINUED)
15. After attaching the last overhead purlin to the inside
rafter, move down the rafter assembly to the pipe joint
below the rafter chord and place a cross-connector
(#102546) over the rafter pipe.
This inserts shows the purlin, clamp and cross-
connector as seen from the inside of the building.
16. Insert the first two sections of the pre-marked purlin
through the cross-connector and into the pipe strap in
the same position on the end rafter. Tighten the pipe
strap and secure the purlin to the pipe strap using a Tek
screw (FA4482).
17. Align the mark on the purlin with the center of the rafter
leg and tighten the cross-connector. The purlin should
be saddled in the pipe joint on the rafter.
18. Install a Tek screw (FA4482) through the cross-
connector and through the joint in the purlin to prevent
separation of the purlin pipe joint.
19. Move to the remaining joint below the rafter chord on
the inside rafter and attach the first two sections of the
next purlin.
The drawing above shows the top 5 purlins in position.
20. Set the next
inside rafter assembly
in position and
secure it to the feet as previously instructed.
21. Continue to add the cross-connectors and the pre-
marked sections of purlins and secure these to the
rafter assemblies as previously instructed.