CLEARSPAN
™
VALUE LINE
18
Revision date: 10.05.10
FINISH ROUGH EDGES
Gather the parts
• Duct tape
• Metal file
1. Check for any sharp edges on the frame and file them
smooth so they will not cut the cover.
2. Apply two layers of heavy duct tape on all pipe
connections and clamps that may contact the cover.
INSTALL THE RATCHETS FOR THE MAIN COVER
All ratchets are
attached on the outside of the assembled
frame
. Complete the following steps to position and secure
the ratchets to the frame.
Gather the parts:
• Large ratchet (#QH1065)
• Tek screws (#FA4482)
Complete the following steps to locate and secure the
ratchets to the rafter legs.
1. Locate all QH1065 ratchets and divide the quantity in
half. Use half for each side of the frame.
2. Place the large ratchets on the ground next to each
rafter. Consult the Quick Start diagrams for proper
location of ratchets.
3. Attach the QH1065 ratchet to the rafter foot using a Tek
screw as shown below.
ATTENTION:
Ratchets are evenly spaced long each
side of the shelter and directly across from each other
on the
same rafter assembly
.
4. After all side ratchets are installed and a final
frame check complete, continue with the end panel
installation procedures.
FINAL FRAME CHECK
1. Verify that all rafter pipe splices and purlin splices are
secured with a Tek screw.
2. Recheck the frame assembly for sharp edges or
clamps and bolts that may interfere with the installation
of the cover. Reposition clamps and bolts as needed.
Tape all rafter pipe joints with duct tape to protect the
cover.
3. Check all turnbuckles to verify that they are tight.
4. Tape the loose or frayed ends of all cables to protect
the cover.
5. Verify that all bolts and clamps are tight.