54
3.) Switch the DC Switch to the “ON” position. When the energy supplied by
the PV array is sufficient, the LCD screen of inverter will light up. The inverter
will then start up with the message “sys checking”.
4.) Set up the grid standard:
When the inverter completes “sys checking”, LCD shows the screen as
Figure 4-1 below. Press ENTER to the standard selection interface, as
shown in Figure 4-2.
Select the corresponding grid standard and press ENTER.
Set Standard!
Figure 4-1 Set up grid standard
INSTRUCTION:
Please check with your local electricity supply company before
selecting the grid standard. If the inverter is operated with a wrong grid
standard, the electricity supply company may cancel the operation
license.
Putting the inverter into operation before the overall system complies
with the national rules and safety regulation of the application is not
permitted.