12
1.3.5 Testing New Batteries
For a battery test:
The batteries must be fully charged.
The UPS must be in Normal mode with no active alarms.
Don’t take on/off the load.
To test batteries:
1.
Connect the UPS to utility power for at least 48 hours to charge the batteries.
2.
When UPS is working on line mode or HE mode, go to the “Start battery test” of
“control” menu to implement the test.
1.3.6 Recycling the Used Battery:
Warning:
Never dispose the batteries in a fire. They may explode. Do not open or
modify the batteries.
Released electrolyte is harmful to the skins and eyes. It may be toxic.
A battery can present a risk of electrical shock and high short circuit current.
To recycle the used batteries properly do not dispose of the UPS, battery pack or
batteries into the general waste. Please follow your local laws and regulations, local
refuse authorities can provide further information on proper disposal.
1.4 Transport
Please transport the UPS only in the original packaging.
1.5 Storage
The UPS must be stored in a dry, well ventilated area.
Summary of Contents for C400R-010-B
Page 7: ...3 ...