REFERENCE
EDMS NO.
REV.
VALIDITY
TOF-TAR-PRD-0001
1867100
1.0
RELEASED
Page 45 of 93
Name of task
331. Remove round
shielding block 4
Exposed people
0
Local dose rate
Workforce
2 people
Time needed
0.5 days
Calculated dose
Responsible
EN-STI
Involved
EN-EA/ EN-HE/ HSE-RP
Comments:
Radiation low, shouldn’t be contaminated.
The shielding block will be wrapped depending on
the level of contamination.
It will be stored in ISR8 Storage Area.
To be removed through Technical Gallery trap door
to allow entirety to be done with remote handling.
Telescopic forklift needed to move from beneath the
trap door and into ISR.
To be carried on metal/plastic palette.
Palette to be designed and made by EN-EA.
Shielding blocks drawing: TOFEAR2_0061.
RP will measure the blocks for signs of contamination
and also the pit once block 2 has been removed.
Round
shielding
block 4
Round
shielding
block 3
Round
shielding
block 2
Round
shielding
block 1
Summary of Contents for ATOMTEX BDKG-24
Page 62: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 62 of 93...
Page 65: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 65 of 93...
Page 68: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 68 of 93...
Page 73: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 73 of 93...