First steps
–
✓
Check polarity and voltage (close to “Nº modules connected x 48Vdc”) on
the power connector below the MCP.
✓
Use the multimeter to check that there is no continuity between positive and
negative on the MCP power connector (no beep)
✓
If everything is OK, proceed to connect the MCP connector to the already
connected DC BUS connector.
9. At the back of the MCP, connect the earth connection (M-6 bolt) to the earth for
the installation. An earth cable of between 1mm
2
- 2.5 mm
2
section should be
used (See point 7 in image below)
10. Check at the back of the MCP that there is no voltage or continuity between the
poles on the positive and negative power output connectors. (See points 4 and 6
in image below)
11. At the back of the MCP connect the terminals (M-8) that corresponds to the
installation’s positive and negative terminals. The recommended tightening
torque is 10Nm using a torque wrench. (See points 4 and 6 in image below)
12. At the back of the MCP connect the correct RJ45 communication connectors for
the inverter (MODBUS or CAN BUS). It is recommended that the cable length is
no longer than 20 metres.