![CE+T Power Bravo 10 - 48/230 User Manual Download Page 38](http://html1.mh-extra.com/html/ce-t-power/bravo-10-48-230/bravo-10-48-230_user-manual_2577177038.webp)
12.1 Check list
DATA
Date
Performed by
Site
System serial number
Module serial numbers
Inview GW/S/X Serial number
ACTION
OK/ N.OK
Unplug all inverters except one inverter per phase (Just pull off the inverter from the shelf, to interrupt
electrical contacts)
Check the commercial AC before closing the AC input breaker.
Switch ON the commercial AC
Check if inverters are working (Green led)
Check the DC power supply and switch ON the DC breakers
Plug in all inverters one by one
Check output voltage (on bulk output or on breaker)
Check if inverters are working properly
Check if system has no alarm (Disable the alarm if any)
Read configuration file and review all parameters. Some parameters should be adapted according to the site
condition.
Switch OFF AC IN and check if system is working on DC
Switch ON AC IN and check if system correctly transferred load on AC
Switch OFF system and start on AC only
Switch OFF system and start on DC only
Check if display working properly (if this Inview option is present)
Test on load (if available)
ALARM
Switch ON AC input and DC input and check that no alarm are present
Pull out one inverter and check alarm according to redundancy
Pull out two inverters and check alarm according to redundancy
Switch OFF AC input (commercial power failure) and check the alarm according to the configuration
Switch OFF DC input (DC power failure) and check that the alarm according to the configuration
Check the different digital input according to the configuration (when used)
Commissioning
38