12. Commissioning
The DC breaker is a protection device. Modules are plugged in a system and DC breaker is then engaged. Please make
sure the corresponding DC breaker is engaged in the ON position. Failure to observe this rules will result not to have all
module operating when running on DC and have module failure when AC input recover from fault condition.
Installation and commissioning must be done and conducted by trained people fully authorized to act on installation.
It is prohibited to perform any isolation test without instruction from manufacturer.
Equipments are not covered by warranty if procedures are not respected.