115-V WIRING
Verify that the voltage, frequency, and phase correspond to that specified
on unit rating plate. Also, check to be sure that service provided by
utility is sufficient to handle load imposed by this equipment. Refer to
rating plate or
for equipment electrical specifications.
U.S. Installations:
Make all electrical connections in accordance with
National Electrical Code (NEC) NFPA 70 and any local codes or
ordinances that might apply.
Use a separate, fused branch electrical circuit with a properly sized fuse
or circuit breaker for this furnace. See
for wire size and fuse
specifications. A readily accessible means of electrical disconnect must
be located within sight of the furnace.
NOTE:
Proper polarity must be maintained for 115-v wiring. If polarity
is incorrect, control LED status indicator light will show rapidly and
furnace will NOT operate.
A190279
Fig. 23 – Copper Wire Only
J-BOX RELOCATION
NOTE:
If factory location of J-Box is acceptable, go to next section
(ELECTRICAL CONNECTION to J-Box).
NOTE:
On 14-in. (356 mm) wide casing models, the J-Box shall not be
relocated to other side of furnace casing when the vent pipe is routed
within the casing.
1. Remove and save two screws holding J-Box, see
NOTE:
The J-Box cover need not be removed from the J-Box in order
to move the J-Box. Do NOT remove green ground screw inside J-Box,
.
2. Cut wire tie on loop in furnace wires attached to J-Box.
3. Move J-Box to desired location.
4. Fasten J-Box to casing with the two screws removed in Step 1.
5. Route J-Box wires within furnace away from sharp edges, rotating
parts and hot surfaces.
A10291
Fig. 24 – Relocating J-Box
WARNING
!
ELECTRICAL SHOCK, FIRE OR EXPLOSION HAZARD
Failure to follow safety warnings could result in dangerous operation,
serious injury, death or property damage.
Improper servicing could result in dangerous operation, serious injury,
death or property damage.
- Before servicing, disconnect all electrical power to furnace.
- When servicing controls, label all wires prior to disconnection.
Reconnect wires correctly.
- Verify proper operation after servicing.
WARNING
!
ELECTRICAL SHOCK HAZARD
Failure to follow this warning could result in personal injury or death.
Blower access panel door switch opens 115-v power to control. No
component operation can occur. Do not bypass or close switch with
panel removed.
WARNING
!
ELECTRICAL SHOCK AND FIRE HAZARD
Failure to follow this warning could result in personal injury, death, or
property damage.
The cabinet
MUST
have an uninterrupted or unbroken ground
according to NEC NFPA 70 or local codes to minimize personal injury
if an electrical fault should occur. This may consist of electrical wire,
conduit approved for electrical ground or a listed, grounded power cord
(where permitted by local code) when installed in accordance with
existing electrical codes. Refer to the power cord manufacturer’s
ratings for proper wire gauge. Do not use gas piping as an electrical
ground.
CAUTION
!
FURNACE MAY NOT OPERATE HAZARD
Failure to follow this caution may result in intermittent furnace
operation.
Furnace control must be grounded for proper operation or else control
will lock out. Control must remain grounded through green/yellow wire
routed to gas valve and manifold bracket screw.
WARNING
!
FIRE HAZARD
Failure to follow this warning could result in personal injury, death, or
property damage.
Do not connect aluminum wire between disconnect switch and furnace.
COPPER
WIRE ONLY
ELECTRIC
DISCONNECT
SWITCH
ALUMINUM
WIRE
Factory
Factory
Installed
Installed
Alternate
Alternate
Location