2 - DELIVERY AND HANDLING
2.1 - Receiving and storing the unit
The condition of the unit must be inspected upon receiving it.
In case of damage,
specify this in full on the delivery note
,
indicating the type of problem (upper panel dented, coil damaged,
etc.).
Confirm your observations concerning the damage with the carrier
by registered letter within 48 hours of delivery and send a copy
to yourCARRIERrepresentative.
NB: terms such as "pending unwrapping" and "unit damaged
but packaging in good condition" are not admissible by
insurance companies.
For all other problems, please contact your CARRIER
representative for further information.
The unit must be stored in its packing and sheltered from weather.
To facilitate the assembly of multisplit units, their components
must be kept in the relevant groups. Refer to the dimensional
drawings and identification labels placed on each section (see
below).
39 CZ ST 75
B
C
D
E
F
G
H
I
J
K
B
Order number. Use in all correspondence.
C
Section number
A1, A2, ….A9: multi-section unit.
A second unit may bear the markings B1, B2, ….B9.
The numbers 1, 2 and 3 do not necessarily indicate the order of assembly
(refer to the dimensional drawing).
A9, B9…: markings for all accessories: assembly, roofs, canopies, gaskets,
fastenings, etc. of the corresponding unit.
D
CARRIER internal production order.
E
CARRIER internal coding.
F
Your name or company.
G
Internal pre-shipping check.
H
Your reference (if applicable).
I
Weight of corresponding block.
J
Block year of manufacture.
K
Centre of gravity to facilitate positioning of the lifting beam.
2.2 - Location
The air handling units are relatively large. Extra attention is
required when choosing where to place them.
As is generally the case with boilers and refrigeration units, we
recommend installing the air handling units in machine rooms that
are sufficiently insulated from adjoining rooms.
It is also important to leave sufficient space around the units to
allow access to the various components: bearings, belts, motors,
filters, coils, etc. Refer to the diagram below to ensure trouble-free
maintenance.
IMPORTANT: a clearance of 600 mm is recommended for
assembling the sections
5