1. Pass the piping through the hole in the wall.
2. Put the upper claw at the back of the indoor unit on
the upper hook of the installation plate, move the
indoor unit from side to side to see that it is securely
hooked.
3. Piping can easily be made by lifting the indoor unit
with a cushioning material between the indoor unit
and the wall. Get it out after finish piping.
4. Push the lower part of the indoor unit up on the wall,
Then move the indoor unit from side to side, up and
down to check if it is hooked securely.
Upper hooker
Low hooker
Cushioning
material