background image

Step 5 — Configure Unit for Minimum Load Con-
trol —

Once the piping installation and wiring installation

are complete, the chiller must be configured for minimum
load control operation. This may be done using the unit key-
pad (HSIO-2). Set the LOCAL/OFF switch in the OFF
position.

1. Press

on the keypad.

2. Press the down arrow

until the display reads:

MIN. LOAD VALVE SELECT
DISABLE

3. To enable the minimum load valve feature, press

.

4. The display may read as follows. (If not, skip to Step 7.)

PASSWORD PROTECTED FUNCTION
ENTER PASSWORD

5. Press

.

6. The HSIO-2 again displays the following:

MIN. LOAD VALVE SELECT
DISABLE

7. Press

. The display changes to:

MIN. LOAD VALVE SELECT
ENABLE

The chiller is now configured for minimum load valve
control.

Step 6 — Test Minimum Load Relay Outputs

After the accessory components are installed and the unit

is recharged and reconfigured, test the operation of the relay
and solenoid valve using the Quick Test software function.
Test Circuit A as follows (the LOCAL/OFF switch must be
in the OFF position):

1. Press

on the HSIO-2 keypad.

2. Press the down arrow

until the display reads:

MIN. LOAD VALVE A
RELAY IS OFF

3. Press

.

4. The display may read as follows. (If not, skip to Step 7.)

PASSWORD PROTECTED FUNCTION
ENTER PASSWORD

5. Press

.

6. The HSIO-2 again displays the following:

MIN. LOAD VALVE A
RELAY IS OFF

7. Press

to energize the relay. The display reads:

MIN. LOAD VALVE A
RELAY IS ON
An audible click will be heard. Verify that the solenoid
valve for Circuit A is energized.

8. Press

to turn off the minimum load valve relay

for Circuit A.

To check the operation of the solenoid valve on Circuit B,

follow the same procedure as the preceding, but enter

enter

in Step 1, instead of

. The display

screens will be for Circuit B instead of A.

After testing is complete, recheck all electrical connec-

tions for proper location and tightness. For 30HX units, re-
place and secure the access panels for the unit control box.
For 30GX units, secure the junction box covers to the junc-
tion boxes.

Step 7 — Adjust Setting of Minimum Load Ball
Valve —

Before the installation is complete, the mini-

mum load ball valve must be adjusted to suit the application.
Calibrate one circuit at a time as follows:
1. Adjust the ball valve so that it is approximately half open.
2. Operate the chiller in Manual Control mode, with one cir-

cuit operating, and all compressor loaders deenergized.

NOTE: Operation of the chiller in Manual Control mode is
described in the Controls, Start-Up, Operation, and Trouble-
shooting Guide that is included with the 30GX,HX
Ecologic™ chillers.
3. Record the cooler

D

T (the difference between cooler en-

tering fluid temperature and cooler leaving fluid tempera-
ture) at this fully unloaded condition.

4. Use the Manual Control feature to enable the minimum

load valve for the circuit that is operating.

5. Observe and record the cooler

D

T with the minimum load

valve energized.

6. Adjust the minimum load ball valve until the cooler tem-

perature difference reading from Step 5 is equal to half of
the temperature difference reading from Step 3.

7. Open the ball valve to decrease the temperature differ-

ence or close the ball valve to increase the temperature
difference (

D

T). When the valve is adjusted correctly,

the difference between cooler entering and leaving fluid
temperatures when the minimum load control is ener-
gized must be at least half of the temperature difference
when the minimum load control is deenergized. For ex-
ample, if the difference between the cooler entering and
leaving water temperature is 3° F with the valve deen-
ergized, then the difference between cooler entering and
leaving water temperature must be at least 1.5° F with the
valve energized.

Once the outputs have been tested and the ball valve ad-

justed, the installation is complete.

6

Summary of Contents for 30GX080-176

Page 1: ...ully unloaded condition The accessory provides more precise control of leaving fluid temperature during light load conditions The 30GX and 30HX chillers have a dual circuit design Each minimum load co...

Page 2: ...t braze nipple on discharge line located between oil separator and con denser Remove plug from minimum load port on cooler shell See Fig 1 Using thread sealant install Swagelok fitting in minimum load...

Page 3: ...bottoms out tighten the compression nut finger tight while holding the fitting body Use backup wrench to hold fitting body and tighten compression nut another 11 4 turns IMPORTANT Do NOT overtighten t...

Page 4: ...ncluded with this kit in the position shown on the 30GX chiller in Fig 3 Route the waterproof conduit included with this kit between the accessory junction box and the factory installed junction box S...

Page 5: ...30GX080 176 30HX076 271 LEGEND MLC Minimum Load Control TB Terminal Block NOTE See Fig 3 for locations of junction boxes on unit Fig 4 Minimum Load Control Wiring 5...

Page 6: ...electrical connec tions for proper location and tightness For 30HX units re place and secure the access panels for the unit control box For 30GX units secure the junction box covers to the junc tion...

Page 7: ......

Page 8: ...ufacturer reserves the right to discontinue or change at any time specifications or designs without notice and without incurring obligations Book 2 Tab 5c PC 903 Catalog No 563 056 Printed in U S A Fo...

Reviews: