background image

9

Water connections

Refer to the certified dimensional drawings for the sizes and
positions of all water inlet and outlet connections. The water
pipes must not transmit any radial or axial force to the heat
exchangers or any vibration to the pipework or building.

The water supply must be analysed and appropriate filtering,
treatment, control devices, isolation and bleed valves and
circuits built in, as necessary. Consult either a water treatment
specialist or appropriate literature on the subject.

Operating precautions
The water circuit should be designed to have the least number
of elbows and horizontal pipe runs at different levels. Below
the basic checks to be done (see also the illustration of a typical
hydraulic circuit below).

Note the water inlets and outlets of the heat exchangers.

Install manual or automatic air purge valves at all high
points in the water circuit.

Use an expansion chamber or an expansion/relief  valve to
maintain pressure in the system.

Install water thermometers in both the entering and
leaving water connections close to the evaporator.

Install drain valves at all low points to allow the whole
circuit to be drained.

Install stop valves, close to the evaporator, in the entering
and leaving water lines.

Use flexible connections to reduce the transmission of
vibration to the pipework.

Insulate all pipework, after testing for leaks, both to
reduce thermal leaks and to prevent condensation.

Cover the insulation with a vapour barrier.

Water-loop connections
Make the water-side heat exchanger connections, using
appropriate hardware capable of ensuring water-tightness of
threaded unions.

The illustration below shows a typical hydraulic circuit.

IMPORTANT: In winter frost can cause cooler damage. Use
appropriate methods of protection, according to the climatic
conditions:

Add ethylene glycol.

Increase the insulation thickness.

Do not de-energize the cooler heaters.

For a prolonged shutdown period, drain the water from
the cooler and replace it with ethylene glycol. At the
beginning of the next cooling season, refill the cooler and
add the recommended inhibitor.
Auxiliary equipment should be installed according to
basic refrigeration and piping practices, especially with
respect to minimum and maximum cooler water flow
rates, which must be between the values given in the
tables in the 'Application data' section.

Typical hydraulic circuit diagram

Control valve

Air vent

Flow switch

Flexible connection

Heat exchanger

Fill valve

Expansion tank

Filter

Buffer tank

Drain

Pressure tap

Thermostat sleeve

Summary of Contents for 30GH 040

Page 1: ...and maintenance instructions 30GH 040 245 30GZ 040 245 Air cooled liquid chillers 50 Hz Carrier is participating in the Eurovent Certification Programme Products are as listed in the Eurovent Directo...

Page 2: ...hecks 10 Actual start up 10 Servicing refrigeration components 11 General maintenance 11 Liquid refrigerant charging 11 Compressors 12 Compressor protection circuit board STARTERGUARD 12 Heat exchange...

Page 3: ...temperature C Pressure drop air kPa Pressure drop water kPa Discharge air pressure Pa Fan speed r s or rpm Fan motor input Ph 1 V Ph 2 V Ph 3 V Ph 1 V Ph 2 V Ph 3 V Ph 1 V Ph 2 V Ph 3 V Ph 1 V Ph 2 V...

Page 4: ...85 145 Do not obstruct 30GH GZ A B C D E F G 040 045 2450 1870 1912 2500 1200 500 1200 050 060 2900 2156 2060 2500 1200 500 1200 085 100 3404 2328 2471 1600 1800 1600 1800 120 145 4322 2328 2471 1600...

Page 5: ...not obstructed At least two sides of the units must be free from obstructions to ensure proper air flow If several units are installed next to each other ensure that the space in between the units is...

Page 6: ...150 DN150 Drain NPT in 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 Max water side operating pressure kPa 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000...

Page 7: ...ing of the liquid water or brine Refer to the examples below NOTE The compressor must not restart more than 6 times in an hour INSTALLATION SAFETY CONSIDERATIONS Installation start up and servicing th...

Page 8: ...Siting Before siting the unit check that the permitted loading at the site is adequate or that appropriate strenghtening measures have been taken the surface is horizontal flat and intact there is ade...

Page 9: ...valves close to the evaporator in the entering and leaving water lines Use flexible connections to reduce the transmission of vibration to the pipework Insulate all pipework after testing for leaks b...

Page 10: ...he lubricating oil from absorbing refrigerant Check the operation of all accessories chilled water circulating pumps air handlers and other equipment connected to the evaporator Follow the individual...

Page 11: ...H or 12 K 30GZ of subcooling as the liquid refrigerant enters the expansion valve The units 30GH GZ 040 245 use refrigerant For your information we are reproducing here some extracts from the official...

Page 12: ...xchangers Evaporator Protection devices Freeze up prevention thermostat The evaporator is protected against freeze up The protection is provided by two sensors installed in the unit Significant underc...

Page 13: ...r Carrier distributor Replacing cooler tubes Retubing must be done only by a properly trained service engineer Most standard practices can be applied but for cooler tubes a 5 crush allowance is made f...

Page 14: ...or rotating water jets are strictly forbidden Correct and frequent cleaning approximately every three months will prevent 2 3 of the corrosion problems Fan motor replacement This presents no special p...

Page 15: ...efective compressor Refrigerant losses Refrigerant losses Low water flow in the evaporator Blocked expansion valve Blocked filter drier Defective high pressure switch Defective fan s Low water flow in...

Page 16: ...7 Supersedes order No 13187 76 July 1996 Printed on Totally Chlorine Free Paper Manufacturer reserves the right to change any product specifications without notice Printed in the Netherlands Manufactu...

Reviews: