background image

4

VALVE CORE

SERVICE VALVE

A14236

Fig. 5 – Vapor Service Valve

Brazing Connections

Connect vapor tube to fitting on outdoor unit vapor service valves

(see Table 2). Connect liquid tubing to adapter tube on liquid

service valve if the valve contains a piston body or connect directly

to the liquid service valve if the unit uses an outdoor TXV.

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment

damage or improper operation.
Service valves must be wrapped in a heat–sinking material

such as a wet cloth while brazing.

Apply heat absorbing paste or heat sink product between service

valve and joint. Wrap service valves with a heat sinking material

such as a wet cloth.
After wrapping service valve with a wet cloth, tubing set can be

brazed to service valve using either silver bearing or non–silver

bearing brazing material. Do not use soft solder (materials which

melt below 800

°

F/427

°

C). Consult local code requirements.

NOTE

: Some outdoor units contain a mechanical fitting at the

liquid distributor. This connection is not field serviceable and

should not be disturbed.

NOTE

: For Liquid Service Valve with Piston Body -- Braze

lineset to adapter tube BEFORE bolting adapter to valve. This
helps prevent overheating and damage to plastic washer or o--ring.
For Vapor Service Valves and Liquid Service Valves with No
Piston Body -- remove valve core from schrader port on Service

Valve BEFORE brazing. This helps prevent overheating and
damage to valve seals (refer to Fig. 5). Replace valve core when

brazing is completed.

FIRE HAZARD

Failure to following this warning could result in personal

injury, death and/or property damage.
Refrigerant and oil mixture could ignite and burn as it escapes

and contacts brazing torch. Make sure the refrigerant charge is

properly removed from both the high and low sides of the

system before brazing any component or lines.

!

WARNING

Clean line set tube ends with emery cloth or steel brush. Remove

any grit or debris.
Insert line set tube ends into service valve tube stubs.
Apply heat absorbing paste or heat sink product between service

valve and joint. Wrap service valves with a heat sinking material
such as a wet cloth.
Braze joints using a Sil--Fos or Phos--copper alloy.

Table 2 – Refrigerant Connections and Recommended Liquid

and Vapor Tube Diameters (In.)

UNIT SIZE

LIQUID

RATED VAPOR

Connection

Diameter

Tube

Diameter

Connection

Diameter

Tube

Diameter

25HCC5, 25HPB6

18, 24

3/8

3/8

5/8

5/8

30, 36,

3/8

3/8

3/4

3/4

42, 48

3/8

3/8

7/8

7/8

60

3/8

3/8

7/8

1–1/8

25HCC5 ONLY

37

3/8

3/8

3/4

3/4

* Units are rated with 25 ft. (7.6 m) of lineset. See Product Data sheet for performance

data when using different size and length linesets.

Notes

:

1. Do not apply capillary tube or piston indoor coils to these units.

2. For Tubing Set lengths between 80 and 200 ft. (24.38 and 60.96 m) horizontal or

20 ft. (6.09 m) vertical differential 250 ft. (76.2 m) Total Equivalent Length, refer to

the Residential Piping and Longline Guideline – Air Conditioners and Heat Pumps

using Puron refrigerant.

Install Liquid Line Filter Drier Indoor

Refer to Fig. 6 and install filter drier as follows:

1. Braze 5 in. (127 mm) liquid tube to the indoor coil.
2. Wrap filter drier with damp cloth.
3. Braze filter drier to 5 in. (127 mm) long liquid tube from

step 1.

4. Connect and braze liquid refrigerant tube to the filter drier.

IMPORTANT

: Installation of the filter drier in liquid line is

required.

A05227

Fig. 6 – Liquid Line Filter Drier

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment damage

or improper operation.
Installation of filter drier in liquid line is required.

Evacuate Refrigerant Tubing and Indoor Coil

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment

damage or improper operation.
Never use the system compressor as a vacuum pump.

Refrigerant tubes and indoor coil should be evacuated using the

recommended deep vacuum method of 500 microns. The alternate
triple evacuation method may be used (see triple evacuation

procedure in service manual). Always break a vacuum with dry
nitrogen.

Deep Vacuum Method

The deep vacuum method requires a vacuum pump capable of

pulling a vacuum of 500 microns and a vacuum gage capable of

accurately measuring this vacuum depth. The deep vacuum method
is the most positive way of assuring a system is free of air and

liquid water. A tight dry system will hold a vacuum of 1000
microns after approximately 7 minutes. (See Fig. 7.)

Summary of Contents for 25HPB6

Page 1: ...suitable warning label EXPLOSION HAZARD Failure to follow this warning could result in death serious personal injury and or property damage Never use air or gases containing oxygen for leak testing o...

Page 2: ...ications Clearance Requirements When installing allow sufficient space for airflow clearance wiring refrigerant piping and service Allow 24 in 609 6 mm clearance to service end of unit and 48 in 1219...

Page 3: ...rements Refer to Table 2 for field tubing diameters There are no buried line applications greater than 36 in 914 4 mm If refrigerant tubes or indoor coil are exposed to atmosphere they must be evacuat...

Page 4: ...valves with a heat sinking material such as a wet cloth Braze joints using a Sil Fos or Phos copper alloy Table 2 Refrigerant Connections and Recommended Liquid and Vapor Tube Diameters In UNIT SIZE...

Page 5: ...hrough power wiring hole provided and into unit control box Connect Ground and Power Wires WARNING ELECTRICAL SHOCK HAZARD Failure to follow this warning could result in personal injury or death The u...

Page 6: ...tem caps after system is opened to refrigerant flow back seated Replace caps finger tight and tighten with wrench an additional 1 12 turn 3 Close electrical disconnects to energize system 4 Set room t...

Page 7: ...up To initiate a forced defrost speedup pins J1 must be shorted with a flat head screwdriver for 5 seconds and RELEASED If the defrost thermostat is open a short defrost cycle will be observed actual...

Page 8: ...r temperature is below 70_F 21 11_C or the outdoor temperature is not in the favorable range adjust charge for line set length above or below 15ft 4 57 m only Charge level should then be appropriate f...

Page 9: ...MANP036 FB4CNP048L FV4CNB006L 3 FPMAN 024 FFMANP031 FB4CNP036L FFMANP037 FV4CN B F 003L FX4DN B F 049L FPMBN 018 FPMAN 024 FFMANP030 FPMAN 036 FV4CN B F 005L 3 FX4DN B F 061L 3 FPMBN 024 FPMAN 030 FFM...

Page 10: ...psig low side with 550 psig low side retard S Use hoses with 700 psig service pressure rating S Leak detectors should be designed to detect HFC refrigerant S Puron as with other HFCs is only compatib...

Reviews: