Un-Crating Requirements
Tools Needed
:
• Impact drill with 1/2" socket - 13mm socket/ratchet will be sufficient for unbolting
• Drill with "Philips" cross bit for unscrewing securing brackets inside the crate
• Utility knife for cutting plastic straps and opening boxes
Space Required
:
6.5m x 5m (21.3ft x 16.4ft)
Space Requirements for Un-crating the Arizona 1300 GT printers
IMPORTANT
The Arizona 1300 GT printers have two cross-brace struts on their base frame. If a strut is bent
during installation, it must be replaced.
Facility Requirements
To install the GT printer, the customer's facility should meet the following requirements:
Hallway width (Minimum): 2.07m (81.5") - This allows for approximately 75mm or 3" of total
clearance.
Door opening (Minimum): 1.67m (66")
NOTE
The printer will be able to fit through the minimum opening assuming there is adequate space
on either side of the door to negotiate it through. A panel on the printer can be removed to
facilitate this operation in situations where the doorway is less than the width of the printer (see
dotted line in Figure 4).
The illustration below will assist you to determine whether the printer can fit through a doorway
or negotiate turns in a corridor. This image is also available on our web site and can be used with
a scale model of your facility to ensure that you can accommodate the printer.
NOTE
The printed version of the image on this page is not to scale - use the file from Customer
Support section of the web site, which is scaled at 1:20).
"https://graphiplaza.cpp.canon/
hardware/product/arizona-1300-current-technical-information/"
Arizona 1300 GT Printers
Chapter 3 - Shipping & Handling
19
Summary of Contents for Arizona 1300
Page 1: ...Arizona 1300 Technical guide Site preparation guide 2021 Canon Production Printing...
Page 2: ...Edition 2021 06 US...
Page 4: ...Contents 4...
Page 5: ...Chapter 1 Introduction...
Page 11: ...Chapter 2 Product Description and Safety Information...
Page 16: ...UV Light Safety 16 Chapter 2 Product Description and Safety Information...
Page 17: ...Chapter 3 Shipping Handling...
Page 25: ...Chapter 4 Specifications and Requirements...
Page 38: ...Customer Network Requirements 38 Chapter 4 Specifications and Requirements...
Page 39: ...Chapter 5 Operator Training...
Page 41: ...Chapter 6 Product Safety Data Sheet...
Page 43: ...Chapter 7 Site Preparation checklists...
Page 48: ...On Remote Service Connectivity Information 48 Chapter 7 Site Preparation checklists...
Page 49: ......