Rev IM/GN-CM-EN/1.0 Copyright© October, 2020 Canadian Solar Inc. 10
bolts, depending on bolt class.
In areas with heavy wind loads, additional mounting points should be used. The system designer and the
installer are responsible for correctly calculating the loads and ensuring that the supporting structure
meets all the applicable requirements.
Mounting method: Bolting
Modules should be bolted at the following hole locations depending on the configuration and loads:
Table 5: Approved bolting methods
Bolting on the short frame side using four standard
mounting holes.
Mounting rails run perpendicularly to the long
frame side.
An additional support bar should be placed below
the module as shown below.
Maximum Load:
Uplift load
≤
2400 Pa
Downforce load
≤
5400 Pa
Compatible module types
:
CS6AH-P and CS6AH-M
Bolting on the short frame side using four standard
mounting holes.
Mounting rails run parallel to the long frame side.
Maximum Load:
Uplift load
≤
2400 Pa
Downforce load
≤
2400 Pa
Compatible module types
:
CS6AH-P and CS6AH-M
Bolting on the long frame side using four innermost
mounting holes.
Mounting rails run perpendicularly to the long
frame side.
Bolting on the long frame side using four innermost
mounting holes.
Mounting rails run parallel to the long frame side.
Maximum Load: