Figure 29: Purpose of Tappings
combinations of LWCO's, consult factory. Also
follow manufacturers instructions furnished with
control.
3. Install the Pressuretrol to the boiler using the 1/4″
x 90° (1-7/8″ x 4″) siphon and the 3/4" NPT x 1/4″
FPT hex bushing.
4. The Pressuretrol must be accurately leveled for
proper operation. It is level when the leveling
indicator hangs freely with its pointer directly over
the index mark inside the back of the case. Level
the controller by carefully bending the steam trap
(siphon loop).
5. Install drain valve supplied by others in tapping B
using the appropriate bushing
6. Install the steam gauge using the 1/2″ NPT x 1/4″
FPT hex bushing.
7. Install the safety valve to the back section as shown
in Figure 43. The safety valve is installed in the tee
provided for blowoff piping.
Safety valve discharge piping must be piped
to within six (6) inches of floor or to floor drain
to eliminate potential of severe burns. Do not
pipe in any area where freezing could occur. Do
not install any shut-off valves, plugs or caps in
discharge piping.
La tuyauterie de décharge de la soupape de
sécurité doit être raccordée à moins de six (6)
pouces du plancher ou au drain de plancher
pour éliminer le potentiel de brûlures graves. Ne
pas installer de tuyaux dans des zones où le gel
pourrait se produire. Ne pas installer de vannes
d'arrêt, de bouchons ou de capuchons dans la
tuyauterie de refoulement.
8. For boilers with tankless heaters, install the
operating control in an unused tapping through one
of the heater plates.
9. Plug extra tappings.
J.
WATER BOILERS - INSTALL WATER TRIM
Items for water trim are located in the water trim carton
(except for the separately ordered low water cutoff,
tankless heater control and Sage SBC Parts carton).
Table IV and Figure 29 shows the proper tappings for
each item.
TAPPING SIZE
STEAM BOILER
WATER BOILER
A
4"
Supply
Supply
B
3"
Return
Return
C
3"
Safety Valve
Relief Valve
D
1½"
Crown Inspection / Washout *
Crown Inspection / Washout *
E1
1"
Float L.W.C.O.
Float L.W.C.O.
E2
1"
Float L.W.C.O.
Float L.W.C.O.
F1
1"
Upper Auxiliary Float
L.W.C.O. Connection *
-----
F2
1"
Lower Auxiliary Float
L.W.C.O. Connection
-----
G
¾"
-----
Probe L.W.C.O.
H
¾"
-----
Auxiliary Probe L.W.C.O.
J
¾"
Firing Rate Pressure Control
Firing Rate Temperature Control
K1
¾"
Operating Pressure
Limit Control
Operating Temperature
Limit Control
K2
¾"
High Pressure Limit Control/
Manual Reset
High Temperature Limit Control/
Manual Reset
L
½"
Gauge Glass
Not Used - Plug
M
½"
Steam Gauge (Bush to ¼")
Temperature/Pressure Gauge
N
¾"
-----
Auxiliary Tapping *
P
¾"
Low Fire Hold Control
Low Fire Hold Control
* Special Order Only
Table IV: Purpose of Tappings
Summary of Contents for V1104H
Page 10: ...10 SECTION I GENERAL INFORMATION Figure 1 Dimensional Information...
Page 18: ...18 V11H SECTION ARRANGEMENT Figure 8...
Page 24: ...24 SECTION III INSTALLATION INSTRUCTIONS Figure 15 Bare Boiler Assembly...
Page 28: ...28 Figure 20 V11H Series Jacket Assembly Boiler Models V1104H Thru V1112H...
Page 29: ...29 Figure 21 V11H Series Jacket Assembly Boiler Models V1113H Thru V1123H...
Page 33: ...33 Figure 28 Minimum Piping Recommendations for V11H Series Tankless Heater Manifolds...
Page 39: ...39 Figure 32 V11H Series Minimum Piping Recommendation Primary Secondary Water...
Page 40: ...40 Figure 33 Minimum Piping Details Bypass With Blend Pump...
Page 44: ...44 0 Figure 37 Minimum Piping Requirements V11H Series Steam Boilers Gravity Return...
Page 49: ...49 Figure 42a DHW Generation with Tankless Coils Storage Tank and Destratification Pump...
Page 50: ...50 Figure 42b DHW Generation with Indirect Water Heater...
Page 69: ...69 Figure 45 V11H Series Jacket Assembly Boiler Models V1104H Thru V1112H...
Page 71: ...71 Figure 46 V11H Series Jacket Assembly Boiler Models V1113H Thru V1123H...
Page 73: ...73 Figure 47 Bare Boiler Assembly...
Page 75: ...75 Figure 47 Bare Boiler Assembly...
Page 78: ...78...
Page 79: ...79...
Page 80: ...80 Burnham Commercial P O Box 3939 Lancaster PA 17604 Revised November 1 2021...