4) Assembly of Z-Flex Z-Vent III:
a) General Notes:
• Non-expanded ends of SVE Series III piping sections may be cut using aviation snips or a 24 thread per inch
hacksaw. File or sand the cut end smooth before assembling. Expanded ends may be cut to adapt the SVE series III to
the vent collar. See the following instructions.
• Support horizontal piping sections at intervals of 48” or less.
• Vertical venting systems must be supported by at least one Z-Flex
fi
re stop. An additional vertical support is required
after any offset and as required by the Z-Vent III installation instructions.
b) Start assembly of the vent system at the boiler. Remove the hose clamp shipped on the FCM vent collar. Bend the
three hose clamp tabs on this collar outward slightly.
c) Clean the exterior of the male end of the
fi
rst piece of pipe and the inside of the vent collar on the boiler. Remove dirt,
grease, and moisture from the surfaces to be sealed. Dry surfaces or allow to dry thoroughly.
d) On the male end of the pipe, apply a ¼” wide bead of high temperature silicone approximately ½ inch from the male
end of the pipe. Apply ¼” beads of silicone along both sides of the longitudinal seam (Fig. 7.18).
e) Insert the male end of the pipe into the boiler vent collar until it bottoms out.
f) Apply an additional bead of silicone over the outside of the joint and smooth out.
g) Replace and tighten the clamp on the vent collar.
h) The female end of each Z-Vent III component has a silicone sealing gasket. Examine all vent components to insure
that the gasket integrity has remained during shipping. Gaskets must be in the proper position or
fl
ue gas could leak
resulting in carbon monoxide poisoning.
i) Align the second piece of pipe with the
fi
rst and push them together as far as they will go, but not less than 1-3/4”.
j) Tighten gear clamp to a minimum torque of 40 in-lbs and a maximum of 50 in-lbs.
k) Repeat Steps (h) – (j) for the remaining Z-Vent III components.
l) In horizontal vent systems, a locking band or gear clamp must be used at either side of the wall penetration to
prevent shifting of the vent system in and out of the wall. This applies to both combustible and non-combustible
walls.
n) Allow the silicone to cure per the silicone manufacturer’s instructions before operating the boiler.
Figure 7.18: Z-Vent III Connection to Vent Collar
Summary of Contents for FREEDOM FCM120
Page 8: ...8 Figure 5 1 Wall Mounting Hole Locations ...
Page 9: ...9 Figure 5 2 Boiler Mounting Hardware ...
Page 11: ...11 Figure 6 1 Boiler Installed In A Confined Space Ventilation Air From Inside ...
Page 31: ...31 Figure 7 21 Condensate Piping Arrangement ...
Page 44: ...44 Figure 10 1 Wiring Connections Diagram ...
Page 45: ...45 Figure 10 2 Ladder Diagram ...
Page 46: ...46 Figure 10 3 Wiring of Isolation Relay for Control of Two Heating Circulators ...
Page 49: ...49 FCM Series Lighting and Operating Instructions ...
Page 55: ...55 FIGURE 12 2 BASIC MENU TREE ...
Page 64: ...64 ...
Page 66: ...66 ...
Page 68: ...68 ...
Page 69: ...69 ...
Page 70: ...70 ...
Page 72: ...72 150 151 152 153 154 155 ...
Page 73: ...73 156 157 158 159 160 161 ...
Page 74: ...74 162 ...
Page 75: ...75 NOTES ...
Page 78: ...78 NOTES ...
Page 79: ...79 NOTES ...
Page 80: ......