Boss Direct / Indirect Installation Guide
7
Handling
Care must be taken when transporting, storing and installing the equipment:
• At least two people should lift the cylinder to prevent injuries.
• The cylinder must be stored in a dry area and must never be dropped during handling.
• Packaging should only be removed at the installation location.
• The cylinder must be installed on a level floor with the required load bearing capability. Installation,
servicing, maintenance and repair must be carried out by a competent person.
• All electrical wiring must be carried out by a qualified electrician and be installed in accordance
with current I.E.E Wiring Regulations.
• A lack of safety devices can lead to potentially fatal injuries, all necessary safety devices must
be installed correctly in the system. The use of an electric immersion may lead to the build up of
electrical potential in the water. This can in turn cause corrosion of the immersion. To prevent this,
ensure the immersion heater, and the hot and cold pipework are correctly bonded and connected
to the earth line.
• If plastic pipes are used they must be approved temperature resistant to 95°C at a pressure of 10bar.
A thermostatic mixer should be installed in the system to prevent the risk of scalding. If there are leaks
found in the system, shut off the cold water stop valve from the main supply and contact a competent
person immediately. Also ensure to isolate the power going to any immersions fitted to the cylinder
What Is Benchmark?
Benchmark places responsibilities on both manufacturers and installers. The purpose is to ensure that
customers are provided with the correct equipment for their needs, that it is installed, commissioned
and serviced in accordance with the manufacturer’s instructions by competent persons and that it
meets the requirements of the appropriate Building Regulations.
The Benchmark Checklist can be used to demonstrate compliance with Building Regulations and
should be provided to the customer for future reference. Installers are required to carry out installation,
commissioning and servicing work in accordance with the Benchmark Code of Practice which is
available from the Heating and Hot Water Industry Council who manage and promote the scheme.
Visit www.centralheating.co.uk
Summary of Contents for BOSS 100
Page 4: ...www bssindustrial co uk 4 ...
Page 31: ...Boss Direct Indirect Installation Guide 31 Cylinder Schematic Electrical Diagram S Plan ...
Page 33: ...Boss Direct Indirect Installation Guide 33 Cylinder Schematic Electrical Diagram Y Plan ...
Page 44: ...www bssindustrial co uk 44 48 Direct Indirect Mains Pressure Benchmark Checklist ...
Page 45: ...Boss Direct Indirect Installation Guide 45 49 Water Storage System Commisioning ...
Page 47: ...Boss Direct Indirect Installation Guide 47 Notes ...