21
New Brunswick Scientific Co., Inc.
User’s Guide
4.6
Installing the I-26/26R Stacking Kit
CAUTION!
If the shaker you will place on the bottom is already mounted on a 17-inch
base, follow these instructions first:
To stack two shakers: (1) remove the 4-inch high section of the base,
(2) remove the base mating supports, (3) move the corner braces from the
4-inch base to the 13-inch base, (4) reinstall the shaker on the 13-inch base.
To stack three shakers: (1) remove the 13-inch high section from the bottom
of the base, (2) remove the base mating supports.
1. Remove the six ½-inch plastic slotted set screws and the three ¼-inch plastic socket set
screws from the top of the shaker installed on the base.
Figure 7: Preparing to Stack Shakers
2. Using the six ½-13 x 1-inch hex head screws, lock washers, and washers provided,
attach the stacking kit stacking rails to the top sides of the unit installed on the base.
Secure the rails in place as shown in Figure 8 on the following page.
3. Install the stacking stop bracket to the top back of the unit installed on the base, using
the three ¼-20 x 5/8-inch hex head screws, lock washers, and washers provided, as
shown in Figure 8 on the following page.